02-20-19 Ophelia Apartments (DRC 4864-16) - 1055 Town and Country Road AGENDA DATE: F EBRUARY 20, 2019 TO: Chair McDermott and Members of the Design Review Committee FROM: Anna Pehoushek, Assistant Community Development Director SUBJECT: Design Review No. 4864-16 – 1055 Town and Country Road, Ophelia Apartments (formerly 999 Town and Country Mixed Use) S UMMARY The applicant proposes to develop the apartment phase of a horizontal mixed-use development project by constructing a new five-story residential apartment building surrounding a six-level parking structure at 1055 Town and Country Road. The project, originally addressed as 999 Town and Country Road was approved by the Planning Commission on August 16, 2017 subject to conditions. Conditions of Approval #12 and #14 of Planning Commission Resolution No. PC 17-17 require Design Review Committee (DRC) approval of final colors, materials, landscaping, and lighting prior to issuance of building permits for the apartments. The DRC meeting minutes are provided as Attachment 7. R ECOMMENDATION - F INAL D ETERMINATION Staff is requesting that the DRC take final action to approve project colors, materials, landscaping and lighting. B ACKGROUND I NFORMATION Applicant : John Hyde, Toll Brothers (originally Nick Marcos, Westcore Town-Country, LLC ) Owner: Toll Brothers Property Location: 999 Town & Country Road General Plan Designation: Urban Mixed Use (UMIX) Zoning Classification: UMU (Urban Mixed Use) Existing Development: Four-story, 98,551 square foot office building with a 5-level parking structure, surface parking lot, and related site improvements. Property Size: 6.0 Acres DESIGN REVIEW COMMITTEE AGENDA ITEM Design Review Committee Staff Report February 20, 2019 Page 2 of 9 Associated Applications: Environmental No. 1856-17 (MND), Tentative Parcel Map No. 0012-16, Major Site Plan Review No. 0866-16 & Administrative Adjustment No. 0254-17 Previous Project Reviews: The DRC recommended project approval to the Planning Commission on June 7, 2017. P UBLIC N OTICE No Public Notice was required for this level of review of the project. E NVIRONMENTAL R EVIEW The proposed project is subject to environmental review per the provisions of the California Environmental Quality Act (CEQA). Mitigated Negative Declaration No. 1856 -17 was prepared for this project and was adopted by the Planning Commission on August 16, 2017 . P ROJECT D ESCRIPTION The original project proposal included the creation of a horizontal mixed-use development project by adding a new multi-family residential building to a commercially developed six-acre site developed with a four-story, 98,551 square foot office building surrounded by surface parking spaces and related landscape/hardscape improvements. The first phase of the project, completed in late 2018, involved construction of a new parking structure to serve the office building and accommodate construction of the apartments on the remaining surface parking lot . Over the course of implementation of Phase 1 of the project, the original applicant, Westcore, sold the apartment portion of the project to Toll Brothers. Therefore, Toll Brothers is now the applicant responsible for bringing forward the colors, materials, landscaping, and lighting for final DRC approval. Phase 2 of the project involves construction of a new five-level, 262-unit apartment building wrapped around a six full levels and one partial level parking structure. The ground floor of the apartment building also contains a leasing office , and combination clubhouse/fitness room. Amenities also include a pool courtyard, a recreational area on the west side of the office parking structure, and a dog park on the north side of the office parking structure. E XISTING A REA C ONTEXT Surrounding properties are primarily commercially developed and are comprised of both office and support retail types of uses. The property is bounded on the north by the SR-22 freeway and on the west by the east-bound SR-22 on/off ramps. Continuing further west on the north side of Town & Country Road is a one-story retail/professional office center and beyond is a three- and four-story apartment development. Immediately adjacent on the east side of the project site is a five-story office building with surface parking lot area. To the south, is the Town & Country Office Park, which consists of a collection of small commercial buildings of one - and two-stories Design Review Committee Staff Report February 20, 2019 Page 3 of 9 with shared surface parking lot areas. This site is slated for complete redevelopment with over 700 multi-family units. A 16-story office building sits immediately southwest of the project site across the shared intersection with the SR-22 freeway ramps served by a multi-level, above ground parking garage. The surrounding development represents an eclectic variety of contemporary architectural styles commonly associated with the 1970s through 1990s. E VALUATION C RITERIA OMC Section 17.10.070 establishes the general criteria the DRC should use when reviewing the project. This section states the following: The project shall have an internally consistent, integrated design theme, which is reflected in the following elements: 1. Architectural Features . a. The architectural features shall reflect a similar design style or period. b. Creative building elements and identifying features should be used to create a high quality project with visual interest and an architectural style. 2. Landscape . a. The type, size and location of landscape materials shall support the project’s overall design concept. b. Landscaping shall not obstruct visibility of required addressing, nor shall it obstruct the vision of motorists or pedestrians in proximity to the site. c. Landscape areas shall be provided in and around parking lots to break up the appearance of large expanses of hardscape. 3. Signage . All signage shall be compatible with the building(s) design, scale, colors, materials and lighting. 4. Secondary Functional and Accessory Features . Trash receptacles, storage and loading areas, transformers and mechanical equipment shall be screened in a manner, which is architecturally compatible with the principal building(s). A NALYSIS /S TATEMENT OF TH E I SSUES The apartment phase of the project has experienced relatively minor design refinements since the DRC’s last review in June 7, 2017. Attachment 2 contains a review of those changes prepared by the project architect. The conceptual elevations and landscape plan approved by the Planning Commission are provided for reference in Attachment 8. Below is a summary of project design elements where modifications were made: Design Review Committee Staff Report February 20, 2019 Page 4 of 9 Issue 1 - Architecture The approved architecture of the apartment building is largely the same, but has undergone changes as described below and as presented in Attachment 3. It should be noted that the decorative panels/louvers discussed over the course of the original project review are not addressed at this time and will return to the DRC for final review and approval. Paint: The white color originally proposed for the exterior plaster of the foreground wall planes has been changed from “Extra White” (SW 7006) to “Neutral Ground” (SW 7568) in response to the painting of the adjacent office building from a beige sandstone to stark white. This color change is intended to offer a subdued warm white complement to the appearance of the office. Stucco: A 16/20 stucco finish is proposed for the non-street facing exterior walls. This finish has been selected to minimize the potential for cracking. The original stucco finish was not specified. Stone Veneer: The originally proposed Coronado stone veneer has been changed to Eldorado Stone. The alternative material is intended to provide a higher quality material with a richer, varied text ure. This choice of veneer will also be color coordinated with the “Nantucket Dune” (SW 7527) paint color that is used as an accent color on the ground floor of the apartments. Siding: Wood siding has been introduced at the corner of the main drive entry/leasing office corner. The look of this siding is meant to tie in with the wood walls integrated into the landscape/hardscape areas affiliated with the adjacent office building. Railings: The original horizontal metal balcony railings on the uppe r floors of the southeast corner of the building (above the leasing office) have been replaced with glass railings. This change has been made to provide a higher quality appearance at this prominent entry corner to the project. Windows: The original white finish of the window frames on the storefront and upper level windows has been changed to black. This color change is proposed to offer an attractive contrast to the new “Neutral Ground” paint color. The black finish also complements the office building windows that are also framed in black. Design Review Committee Staff Report February 20, 2019 Page 5 of 9 Issue 2 - Landscaping and Amenities The final landscape palette (Attachment 4) consists of a diverse variety of trees including palm, eucalyptus, ficus, magnolia, olive, Melaleuca, Crape Myrtle, Tristania, London plane, Trumpet tree, and Umbrella tree. The tree palette is consistent with the palette used in Phase I of the project and contributes to the overall visual integration of the office and apartment components of the site. Larger stature London plane and Tristania will line the sidewalk, contributing to the pedestrian orientation and overall enhancement of the Town and Country streetscap e. The scale of these trees is well suited to both the scale of the apartments and Town and Country street environment. Similarly, the shrub and groundcover choices for the apartment site complement those of the office landscaping. They consist of Giant bamboo, Italian Cypress, dwarf Japanese blueberry, Carolina cherry, Giant Bird of Paradise, and Mauritius hemp. The pool courtyard will be landscaped with multiple varieties of palm trees, magnolias, ficus, and Umbrella trees. Artificial turf will a lso be used in limited portions of the ground plane. Amenities Modifications have been made to the configuration of the pool deck area as well as the half-court basketball court west of the office building parking structure. The configuration of the pool courtyard has changed due to an adjustment in the building footprint related to the design of the clubhouse/lounge area. Additionally, the half-court basketball court has been replaced with an area offering ping pong tables and corn hole boards. This change was made due to a combination of factors including the position of an Edison transformer, and the potential for nuisance noise related to bouncing basketballs in relation to the residential units. The amenity area would continue to be shared recreational space with the office building. A roof deck was not shown on the plans approved by the Planning Commission, however the project now incorporates one at the southwest portion of the building. The roof deck features synthetic turf, decorative pavers, barbeques, a fireplace, decorative pottery, seating areas, and shuffleboard and foosball tables. Issue 3 - Lighting Exterior lighting for the apartments consists primarily of contemporary style landscape lighting in the form of pole lights, bollards, stake mounted tree lighting, and tree mounted down lighting. Overhead string lights, pendent lights, and cabana lights will be used in the common open space areas interior to the site. String lights are also proposed on the east side of the apartments no rth of the vehicular access to the project parking. Cut sheets depicting the proposed light ing are provided in Attachment 5. Design Review Committee Staff Report February 20, 2019 Page 6 of 9 Aside from this lighting, building mounted lighting would consist of recessed fixtures at building entry points. The light poles for the top deck of the parking structure will return to the DRC for review in conjunction with the decorative panels/louvers, and project signage. Issue 4 – Retaining Wall Upon development of grading plans and construction documents, Toll Brothers determined that a retaining wall was needed along the western property line of the site adjacent to the freeway onramp. The wall will be constructed of split face block with a precision wall cap. A 5 -foot high tubular steel fence will be installed on top of the wall. Details of this wall are provided in Attachment 5. A DVISORY B OARD R ECOMMENDATION The interdepartmental Streamlined Multidisciplinary Accelerated Review Team (SMART) recommended Planning Commission approval of the project on March 8, 2017. S TAFF R ECOMMENDATION AND R EQUIRED F INDINGS The courts define a “Finding” as a conclusion which describes the method of analysis decision makers utilize to make the final decision. A decision making body “makes a Finding,” or draws a conclusion, through identifying evidence in the record (i.e., testimony, reports, environmental documents, etc.) and should not contain unsupported statements . The statements which support the Findings bridge the gap between the raw data and the ultimate decision, thereby sho wing the rational decision making process that took place. The “Findings” are, in essence, the ultimate conclusions which must be reached in order to approve (or recommend approval of) a project. The same holds true if denying a project; the decision mak ing body must detail why it cannot make the Findings. The Findings are applied as appropriate to each project. Based on the following Findings and statements in support of such Findings, staff recommends the DRC approve the project with recommended conditions. 1. In the Old Towne Historic District, the proposed work conforms to the prescriptive standards and design criteria referenced and/or recommended by the DRC or other reviewing body for the project (OMC 17.10.070.F.1). This project site is not within the Old Towne Historic District; therefore, the finding is not applicable. 2. In any National Register Historic District, the proposed work complies with the Secretary of the Interior’s standards and guidelines (OMC 17.10.07.F.2). Design Review Committee Staff Report February 20, 2019 Page 7 of 9 This project site is not within the National Register Historic District; therefore, the finding not inapplicable. 3. The project design upholds community aesthetics through the use of an internally consistent, integrated design theme and is consistent with all adopted specific plans, applicable design standards, and their required findings (OMC 17.10.07.F.3). The surrounding built environment is characterized by a variety of architectural styles, ages of buildings, types of development, and sizes. The final colors, materials, landscaping, and light fixtures are consistent with the contemporary architecture of the apartment building and adjacent office development. The apartment landscaping is consistent and complementary to that of the adjacent office landscaping to facilitate a visual integration between the two phases of development. The streetscape landscaping contributes to the pedestrian orientation of Town and Country Road and supports the General Plan goals of transitioning this area of the city into a user-friendly mixed use district with pedestrian linkage between residential, office and retail uses. There is no specific plan or design standards applicable to the site. 4. For infill residential development, as specified in the City of Orange Infill Residential Design Guidelines, the new structure(s) or addition are compatible with the scale, massing, orientation, and art iculation of the surrounding development and will preserve or enhance existing neighborhood character (OMC 17.10.07.F.4). This project is not an infill residential development subject to the City’s Infill Residential Design Guidelines; therefore, the finding is not applicable. C ONDITIONS Staff is recommending that the DRC recommend approval of the project design and the environmental analysis of the project Aesthetics Impacts to the PC subject to standard conditions of approval, and additional conditions as deemed appropriate by the Committee to support the required findings and ensure the preservation of community aesthetics. 1. The project shall conform in substance and be maintained in general conformance with plans and exhibits date labeled February 20, 2019 including any modifications required by conditions of approval, and as recommended for approval by the Design Review Committee. 2. Except as otherwise provided herein, this project is approved as a precise plan. After any application has been approved, if changes are proposed regarding the location or alteration of any use or structure, a changed plan may be submitted to the Community Development Director for approval. If the Community Development Director determines that the proposed change complies with the provisions and the spirit and intent of the approval action, and that the action would have been the same for the changed plan as for the approved plan, the Community Development Director may approve the changed plan without requiring a new public hearing. Design Review Committee Staff Report February 20, 2019 Page 8 of 9 3. Subsequent modifications to the approved architecture and color scheme shall be submitted for review and approval to the Community Development Director or designee. Should the modifications be considered substantial, the modifications s hall be reviewed and approved by the Design Review Committee. 4. Prior to the issuance of a certificate of occupancy (including a temporary certificate of occupancy) for the apartment parking structure, the applicant shall submit a Sign Program for the apartments for review and approval by the Design Review Committee. 5. Prior to issuance of a certificate of occupancy (including a temporary certificate of occupancy) for the apartment parking structure, the applicant shall submit the design of the decorative panels/louvers for the apartment building for review and approval by the Design Review Committee. 6. Prior to issuance of a certificate of occupancy (including a temporary certificate of occupancy) for the apartment parking structure, the applicant shall submit the final top deck parking structure light poles/fixtures for review and approval by the Design Review Committee 7. Prior to issuance of a certificate of occupancy for the apartments, all landscaping located within public areas shall include the installation of root barriers acceptable to the Public Works Department on the sidewalk side of the tree, or where conditions warrant, the installation of a Deep Root box as directed by the Public Works Director. 8. Prior to building permit issuance for the apartments, City required irrigation and landscape inspection notes shall be placed on the final landscape plan, to the satisfaction of the Community Services Director. 9. The project is considered a Priority project and will need to prepare and submit a Final Water Quality Management Plan (WQMP) with treatment BMPs and site design features such as more permeable pavements, landscaping infiltration, directing roof runoff into planters and other BMPs that will serve as buffers for runoff from the site. The WQMP shall be approved prior to issuance of building permits. 10. Prior to building permit issuance, the final landscape plan shall be reviewed and approved by the Orange Fire Department. Prior to building permit issuance, final landscaping plans for the project shall be designed to comply with the City’s Water Efficient Landscape Guidelines as described in Section IX of the City of Orange Landscape Standards and Specifications. 11. Prior to issuance of Certificate of Occupancy for both the parking structure and apartment s , the applicant shall schedule a light reading inspection with the Crime Prevention Bureau. The lighting shall be tested and confirmed to determine if the lighting meets or exceeds the exterior boundary standards. The applicant shall use shielding so as to ensure that the light standards meet the requirements of OMC Section 17.12.030 for the areas beyond the property’s exterior boundaries; light spillage or pollution to surrounding residential areas shall not exceed a maintained minimum of 0.5 foot-candle. Design Review Committee Staff Report February 20, 2019 Page 9 of 9 12. The applicant agrees to indemnify, hold harmless, and defend the City, its officers, agents and employees from any and all liability or claims that may be brought against the City arising out of its approval of this permits, save and except that caused b y the City’s active negligence. The City shall promptly notify the applicant of any such claim, action, or proceedings and shall cooperate fully in the defense. 13. The applicant shall comply with all federal, state, and local laws, including all City regulat ions. Violation of any of those laws in connection with the use will be cause for revocation of this permit. 14. Building permits shall be obtained for all construction work, as required by the City of Orange, Community Development Department’s Building Divis ion. Failure to obtain the required building permits may be cause for revocation of this entitlement. A TTACHMENTS 1. Vicinity Map 2. Summary Table of Design Changes, Architects Orange, January 28, 2019 3. Elevations dated February 20, 2019 (date stamped January 2 8, 2019) 4. Landscape Plan dated February 20, 2019 (date stamped January 28, 2019) 5. Lighting Specifications dated February 20, 2019 (date stamped January 28, 2019) 6. Retaining Wall Detail 7. Design Review Committee Minutes, June 7, 2017 8. Approved Conceptual Elevations and Landscape Plans, July 17, 2017 c: John Hyde Senior Project Manager Toll Brothers 200 Spectrum Center Drive, Suite 300 Irvine, CA 92618 jhyde@tollbrothers.com Kara Sutch Architects Orange 321 W. Chapman Avenue Orange, CA 92866 karas@Architectsorange.com Nick Markos Vice President, Asset Management Westcore Properties 4350 La Jolla Village Dr., Suite 900 San Diego, CA 92122 nmarkos@westcore.net N:\CDD\PLNG \Applications \Tentative Parcel Maps \TPM 0012 -16 Town & Country MU \DRC_Rpt_OpheliaApts_2_20_2019.docx