SR - AGR-6530 - RESERVOIR 4 SLOPE REGRADING PROJECT1. SUBJECT
Award of Contract - Bid No. 178 -03; Reservoir 4 Slope Regrading (W -681).
2. SUMMARY
Three bids for the Reservoir 4 Slope Regrading (W -681) project were received and opened on
September 7, 2017. The apparent low bidder is Jeremy Harris Construction, Inc. for $128,063.
3. RECOMMENDED ACTION
Award a contract in the amount of $128,063 to Jeremy Harris Construction, Inc. and authorize
the Mayor and City Clerk to execute the necessary documents on behalf of the City.
4. FISCAL IMPACT
Funds are budgeted and are available in the following account:
600.8011.51401.00000 Repairs to buildings and fixed equipment $128,063
5. STRATEGIC PLAN GOAL(S)
Provide for a safe community:
b. Provide and maintain infrastructure necessary to ensure the safety of the public.
2. Be a fiscally healthy community:
b. Effectively manage and develop City assets.
4. Provide outstanding public service:
b. Provide facilities and services to meet customer expectations.
6. GENERAL PLAN IMPLEMENTATION
Infrastructure Element Goal 6.0: Ensure water, sewer, and storm drain systems that meet the
needs of residents and businesses.
Policy 1.1: Provide sufficient levels of water, sewer, and storm drain service throughout the
community.
Economic Development Element Goal 6.0: Provide sufficient infrastructure to support
anticipated economic development and growth.
Policy 6.1: Provide public improvements to support commercial, industrial and institutional
uses.
7. DISCUSSION and BACKGROUND
Reservoir 4 lies in the southeastern part of town and consists of a 5 million gallon partially
buried reservoir along with a newer pump station situated directly adjacent to the tank. The
reservoir stores water for the lower pressure zone for the southern part of the City.
While the tank was constructed first in the late 1960's, subsequent tract home construction has
built up the site such that the tank site now lies nestled behind an existing residential housing
tract. To maintain their properties, the adjacent neighbors have built an array of block wall
fences on the rear property line adjacent to the tank site.
In order to improve drainage conditions and to alleviate potential hydraulic pressure in the
ground against the existing freestanding block walls separating the reservoir site and adjacent
neighbors, the Water Division will clean up, regrade, and install a concrete V -ditch behind these
walls along the toe of the reservoir's southerly slope.
A topographic survey has been conducted and construction grading plans have been prepared by
the City's consultant, Joseph C. Truxaw and Associates, Inc.
On June 13, 2017, the City Council approved advertisement for this bid. The bids were received
and opened on July 20, 2017. Three bidders responded as follows:
CONTRACTOR
AMOUNT
1 Jeremy Harris Construction, Inc.
$128,063
2 Earth Construction & Mining
$144,800
3 Minako America Corporation
$389,770
Staff has conducted a license check for the lowest bidder, Jeremy Harris Construction, Inc. In
addition, all reference agencies and companies contacted for the respective bidder have provided
positive feedback and good reviews.
ITEM 2 10/24/17
Construction is anticipated to begin in January 2018 and should be completed within 45 calendar
days.
8. ATTACHMENTS
• Bid Abstract
• Contract Agreement
CITY COUNCIL MINUTES OCTOBER 24, 2017
3. CONSENT CALENDAR (Continued)
3.10 CLAIMS (C3200.0)
The following claim(s) have been received and investigated by the City Attorney's Office
and /or the Risk Manager. After a thorough investigation with the involved departments, it
is the recommendation of the City Attorney's Office that the claim(s) be denied.
a. Loida Romero
b. Heather Steves
c. Sedwick a/s /o Andrea Lundeen
d. Khashayar Lessani
e. eCompliance, Inc.
f. Cathi Budd
g. Estate of Andy Huy Huu Hoang
ACTION: Denied Claim(s) for damages and referred to City Attorney and Claims Adjuster.
3.11 Award of Contract for Bid No. 178 -06; Katella Avenue Sidewalk Improvements.
(A2100.0; AGR -6528)
ACTION: Accepted the lowest bid and awarded the contract to Aramexx Group, Inc. of
Claremont, California, in the amount of $199,884 and authorized the Mayor to execute and
the City Clerk to attest the contract on behalf of the City.
3.12 Award of Contract for Bid No. 178 -08; two (2) Federal Highway Safety Improvement
Program (HSIP) Left -Turn Phasing Signal Modification Projects: 1) Collins Avenue
at Batavia Street; and 2) Chapman Avenue at Cannon Street. (A2100.0; AGR -6529)
ACTION: 1) Authorized the appropriation from the 284 unreserved TSIP fund balance to
the following expenditure account: 284.5032.56100.30027 — HSIP6 Batavia and Collins,
$77,000; 2) Authorized the appropriation from the 271 unreserved Gas Tax Construction
fund balance to the following expenditure account: 284.5032.56100.30028 — HSIP6
Chapman and Cannon, $65,000; and 3) Awarded the contract in the amount of $599,999
to California Professional Engineering, Inc. and authorized the Mayor and City Clerk to
execute on behalf of the City.
3.13 Award of Contract for Bid No. 178 -03; Reservoir 4 Slope Regrading (W -681).
(A2100.0; AGR -6530)
ACTION: Awarded the contract in the amount of $128,063 to Jeremy Harris Construction,
Inc.; and authorized the Mayor and City Clerk to execute on behalf of the City.
3.14 Final Acceptance of Agreement No. 6219, Water Division Antenna Tower
Installation; and authorization to file the Notice of Completion with the County
Recorder. (No staff report required.)
ACTION: Accepted public work improvements, authorized release of U.S. Specialty
Insurance Company of Texas, Bond No. 100275832 in the amount of $280,171.32 to the
contractor on said job, and authorized the Mayor and City Clerk to execute the Notice of
Completion.