SR - AGR-6503 - WALNUT AVENUE STREET IMPROVEMENTS 400 EAST OF MALENA STSUBJECT Award of Contract: Bid No. 167 -43; Walnut Avenue Street Improvements 400 feet east of Malena Street (SP- 3988). 2. SUMMARY Bids for Walnut Avenue Street Improvements (SP -3988) were received and opened on June 20, 2017. Five bidders responded to the Notice Inviting Bids. The apparent low bidder is Palp, Inc. DBA Excel Paving Company of Long Beach, California in the amount of $196,874. 3. RECOMMENDED ACTION Accept the lowest bid, and award the contract to Excel Paving Company of Long Beach, California in the amount of $196,874 and authorize the Mayor to execute and the City Clerk to attest the contract on behalf of the City. 4. FISCAL IMPACT Funds are budgeted in the Capital Improvement Program and are available in the following account: 220.5011.56200.15508 Sewer Line Replacement $ 30,000 272.5011.56330.13120 Pavement Management Program $ 190,000 $ 220,000 5. STRATEGIC PLAN GOAL(S) 1. Provide for a safe community - b. Provide and maintain infrastructure necessary to ensure the safety of the public. G,�•°c� AGENDA ITEM August 08, 2017 TO: Honorable Mayor and Members of the City Council THRU: Rick Otto, City Manager FROM: Joe DeFrancesco, dY Public Works D' ector ReviewedNeriRed City Manager Finance Directo To Be Presented By: Joe DeFrancesco X Cons Calendar City Mgr Rpts Council Reports Legal Affairs Boards /Crates _ Public Hrgs Admin Reports Plan/Environ L SUBJECT Award of Contract: Bid No. 167 -43; Walnut Avenue Street Improvements 400 feet east of Malena Street (SP- 3988). 2. SUMMARY Bids for Walnut Avenue Street Improvements (SP -3988) were received and opened on June 20, 2017. Five bidders responded to the Notice Inviting Bids. The apparent low bidder is Palp, Inc. DBA Excel Paving Company of Long Beach, California in the amount of $196,874. 3. RECOMMENDED ACTION Accept the lowest bid, and award the contract to Excel Paving Company of Long Beach, California in the amount of $196,874 and authorize the Mayor to execute and the City Clerk to attest the contract on behalf of the City. 4. FISCAL IMPACT Funds are budgeted in the Capital Improvement Program and are available in the following account: 220.5011.56200.15508 Sewer Line Replacement $ 30,000 272.5011.56330.13120 Pavement Management Program $ 190,000 $ 220,000 5. STRATEGIC PLAN GOAL(S) 1. Provide for a safe community - b. Provide and maintain infrastructure necessary to ensure the safety of the public. ITEM 3. 1 9 - 1 8/08/17 O Printed on Recycled Paper 4. Provide outstanding public service — b. Provide facilities and services to meet customer expectations. 6. GENERAL PLAN IMPLEMENTATION Infrastructure Element Goal 1.0: Ensure water, sewer, and storm drain systems that meet the needs of residents and businesses. Policy 1.1: Provide sufficient levels of water, sewer, and storm drain service throughout the community. 7. DISCUSSION and BACKGROUND The bid solicitation was advertised on July 5, 2017 for a period of two weeks, and bids were opened on July 20, 2017. Five bidders submitted proposals as follows: 1) Excel Paving Company. Long Beach ............ $196,874.00 2) All American Asphalt, Corona ..................... $224,004.32 3) R.J. Noble., Orange ........ ............................... $265,047.50 4) Hardy & Harper Inc., Santa Ana .................... $276,000.00 5) Harry H. Joh Construction, Inc.., Paramount $537,645.20 The proposed improvements on Walnut Avenue were warranted as a condition of the sale of City surplus property at 2935 E. Walnut Avenue as approved by City Council in December 2016. Once construction is complete all conditions imposed during the sale of the property will be satisfied. Regardless of the sale conditions, the street widening of Walnut Avenue by approximately 12 feet, is needed in order to accommodate two way traffic and facilitate emergency vehicle access. The proposed Street Improvements are categorically exempt from the provisions of the California Environmental Quality Act (CEQA) under CEQA Guidelines Section 15303(d). This project is exempt because it will provide sewer service and improve fire access to vacant parcel 383 -193- 60 (as well as fire access for existing single family residential properties along Walnut Avenue). These improvements will not substantially increase existing street or sewer capacity. The Notice of Exemption has been filed with the County Recorder's Office. Construction is scheduled to begin in September 2017 and is expected to be completed within 45 calendar days. 8. ATTACHMENTS • Bid Abstract JD; EML;cp ITEM 2 8/08/17 Printed on Recycled Paper ) \ \ \ ) a« a! a a s a s ! a■ - a a �- ji - « )�_ k §| w ! : o zz -.� _ _ -2 -_ / ;! w ))!)® _-§ `- |§ _ =n@ z, §£7 \� o j! |ff) $§ !§\){ k \\ 2 _ « a s a a! a s a s ! a■ a ; l�iiBo �. ) §)! k}§ \ \ \ / 2 t &f) ! 2!/ ! a a ! k\( - \ a ! ! @ ! a ! ! ! ! ! # - ` - ! ! ! ! ! a a ! ! ! ■ a § ,§ / ¥ r ■ ! a « ■ ¥ « w ! ! w ) @ ) a« a! a a s a s ! a■ - a a �- ji - « )�_ k §| w ! : o zz -.� _ _ -2 -_ / ;! w ))!)® _-§ `- |§ _ =n@ z, §£7 \� o j! |ff) $§ !§\){ k \\ 2 _ \ \,rr.er- ; l�iiBo �. ) §)! \)\ �2 _\\#f j)�)k)�kfi�fiƒ||! 2 t &f) ! 2!/ k\( - /_ ,¥7 !�: \\ 2 - - - ;{£! �- ji - « )�_ k §| w ! : o zz -.� _ _ -2 -_ / ;! w ))!)® _-§ `- |§ _ =n@ z, §£7 \� o j! |ff) $§ !§\){ k \\ 2 _ \ \,rr.er- ; l�iiBo �. ) §)! \)\ �2 _\\#f j)�)k)�kfi�fiƒ||! 2 t &f) ! 2!/ - /_ ,¥7 !�: \\ 2 - - - ;{£! �- ji - « )�_ k §| w ! : o zz -.� _ _ -2 -_ / ;! w ))!)® _-§ `- |§ _ =n@ z, §£7 \� o j! |ff) $§ !§\){ k \\ 2 _ \ \,rr.er- ; l�iiBo �. ) §)! \)\ �2 _\\#f j)�)k)�kfi�fiƒ||! 2 t &f) ! 2!/