SR - - CITY HALL FACILITIES CONDITION ASSESSMENT1. SUBJECT Facilities Condition Assessment. 2. SU MMARY The Facilities Condition Assessment (FCA) evaluated the condition of 40 city buildings. One of the major goals of the FCA is to calculate the Facility Condition Index (FCI) which rates those buildings. As part of the FCA study, immediate repairs /needs were also identified and are estimated to cost about $2.9 million. 3. RECOMMENDED ACTION Receive and file. 4. FISCAL IMPACT The FCA identifies deficiencies requiring approximately $2.9 million to make improvements to meet immediate demand. It provides the City with the guidance to budget necessary funding through our annual CIP process for improvements that are deemed priorities. 5. STRATEGIC PLAN GOAL(S) 1. Provide for a safe community — b. Provide and maintain infrastructure necessary to ensure the safety of the public. 4. Provide outstanding public service — b. Provide facilities and services to meet customer expectations. 6. GENERAL PLAN IMPLEMENTATION Infrastructure Element Goal 5.0: Ensure lifeline infrastructure systems that meet the City's public health and safety needs. Policy 5.3: Identify engineering vulnerabilities in lifeline utilities exposed to human - caused and natural hazards, including seismic activity, wildland fire, and flooding. 7. DISCUSSION and BACKGROUND Intrndiietinn The City of Orange owns and maintains approximately 40 buildings totaling over 500,000 square feet. The buildings range in age from over 100 years old to less than 10 years old. However, many of the buildings are over 30 years old and require capital reinvestment to ensure their long -term sustainability. As such, the City was in need of a FCA of the various City owned and maintained properties. City Council approved a contract with EMG last March for an FCA that provides a thorough examination and lifecycle assessment of the buildings and major systems including plumbing, mechanical, electrical, roofing, general code compliance, and Americans with Disabilities Act (ADA) compliance. Based on the findings from the completed study, EMG provided a $2.9 million dollar list of Priority 1 (immediate repairs) projects that require immediate action. The Priority 1 list is attached to this report. Staff will evaluate projects on this list prior to making any recommendations for repairs or replacements. A $27.6 million, ten year replacement report was also created for lower priority projects and for anticipated lifecycle replacements. The City Council has been proactively setting aside capital reserves to address infrastructure improvement needs such as those identified in the FCA. The City has also been funding some facility -wide capital improvements through the City's annual CIP budget process. The Civic center HVAC Replacement, the original Main Library Roof Rehabilitation, and the Senior Center Ceiling Improvements totaling $436,000 were programmed last fiscal year. Projects identified for the proposed FY 17 -18 CIP will be presented at the March 28 Budget Study Session. Public Works annually budgets $100,000 in CIP funds to address miscellaneous facility repairs and replacements. As part of the FCA preparation, EMG also updated the City's 20 year old ADA transition plan by examining and evaluating all exterior features of the properties, which included but were not limited to parking lots, sidewalks, access ramps, and all interior areas accessible to the public. EMG identified and prioritized existing improvements needed to meet the 2010 ADA requirements. Those improvements are listed in the order of preference as set by the Department of Justice: physical access to the property; access to areas of commerce or public accommodation; access to public restrooms; and removal of remaining barriers. Analysis EMG evaluated the physical condition of building systems and related components and ranked each of them in one of five conditions as follows: ITEM 2 3/14/17 Excellent: New or very close to new. Component or system typically has been installed within the past year, sound and performing its function. Eventual repair or replacement will be required when the component or system either reaches the end of its useful life or fails in service. Good: Satisfactory as -is. Component or system is sound and performing its function, typically within the first third of its lifecycle. However; it may show minor signs of normal wear and tear. Repair or replacement will be required when the component or system either reaches the end of its useful life or fails in service. Fair Showing signs of wear and use but still satisfactory as -is. Typically near the median of its estimated useful life. Component or system is performing adequately at this time but may exhibit some signs of wear, deferred maintenance, or evidence of previous repairs. Repair or replacement will be required due to the component or system's condition and/or its estimated remaining useful life. Poor Component or system is significantly aged, flawed, functioning intermittently or unreliably. Displays obvious signs of deferred maintenance, shows evidence of previous repair or workmanship not in compliance with commonly accepted standards, has become obsolete, or exhibits an inherent deficiency. The present condition could contribute to or cause the deterioration of contiguous elements or systems. Either full component replacement is needed or repairs are required to restore to good condition, prevent premature failure, and/or prolong useful life. Failed Component or system has ceased functioning or performing as intended. Replacement, repair, or other significant corrective action is recommended or required. One of the major goals of the FCA is to calculate the FCI, which gives an indication of a building's overall condition. Two FCI ratios are calculated and presented, the Current Year and Ten Year. The Current Year FCI is the ratio of Immediate Repair Costs to the building's Current Replacement Value. Similarly, the Ten Year FC1 is the ratio of anticipated Capital Reserve Needs over the next ten years to the Current Replacement Value. FCI CONDITION DEFINITION PERCENTAGE RATING VALUE Good In new or well - maintained condition, with no visual evidence of wear, soiling, or other 0% to 5% deficiencies. Fair Subjected to wear and soiling, but is still in a than 5% to 10 serviceable and functioning condition. Poor Subjected to hard or long -term wear. Nearing the > than 10% to 60 % end of its useful or serviceable life. Very Poor Has reached the end of its useful or serviceable > than 60% life. Renewal is now necessary. Subsequent to determining the condition of the building and systems EMG utilized the following prioritization scheme: ITEM 3 3/14/17 Priority 1: Immediate /Critical Items: Require immediate action to either (a) correct a safety hazard or (b) address the most important building performance or integrity issues or failures. For example, at City Hall it was recommended that the south facing windows be upgraded to double glazed windows and that drinking fountains, restrooms, and access ramps be upgraded to ADA compliant standards. Priority 2: Potentially Critical Items: Include (a) those safety /liability, component performance or building integrity issues of slightly less importance not captured in Priority 1 and/or (b) issues that if left unchecked could escalate into Immediate /Critical items. Accessibility and 'stabilized' environmental issues are also typically included in this subset. For example, paving or sealing the parking lots and upgrading the HVAC controls was recommended under this priority for City Hall. Priority 3: Necessary /Recommended Items: Items of concern that generally either require attention or are suggested as improvements within the near term to: (a) improve usability, marketability, or efficiency; (b) reduce operational costs; (c) prevent or mitigate disruptions to normal operations; (d) modernize the facility; (e) adapt the facility to better meet occupant needs; and/or (f) should be addressed when the facility undergoes a significant renovation. For example, applying a roof reflective coating and upgrading certain HVAC equipment was recommended under this priority for City Hall. Priority 4: Anticipated Lifecycle Replacements: Renewal items which are generally associated with building components performing acceptably at the present time but will likely require replacement or other future attention within the timeframe under consideration. This priority included many components and systems based on their typical service life such as carpeting, painting, HVAC units, electrical switch gears, and variable frequency drives. Opinions of probable costs should only be construed as preliminary, order of magnitude budgets. Actual costs most probably will vary from the consultant's opinions of probable costs depending on such matters as type and design of suggested remedy, quality of materials and installation, manufacturer and type of equipment or system selected, field conditions, whether a physical deficiency is repaired or replaced in whole, phasing of the work (if applicable), quality of contractor, quality of project management exercised, market conditions, and whether competitive pricing is solicited, etc. Conclusion Staff will use the FCA as a planning tool but will always investigate and evaluate every project listed in the FCA prior to investing funds and implementing any projects. The FCA will afford staff a global picture of the condition of the 512,000 ft building space to better our maintenance approach and adopt a more systematic plan. Based on the findings from the FCA, the City will continue to strive to provide funding to the capital reserve fund on an annual basis. Having an adequate capital reserve will allow the city to conduct the necessary reinvestment projects to ensure our facilities are sustainable. 8. ATTACHMENTS -7::::] • FCA Summary Report • City Hall FCA (sample of one of the 40 reports)