HomeMy WebLinkAbout10/9/1989 - Minutes PCPLANNING COMMISSION MINUTES
Special Meeting
City of Orange
Orange, California
October 9, 1989
Monday - 7:30 p.m.
PRESENT: Commissioners Bosch, Greek, Master, Scott
ABSENT: Commissioner Hart (excused from meeting due to a potential
conflict of interest)
STAFF
PRESENT: John Godlewski, Administrator of Current Planning and
Commission Secretary;
Jack McGee, Director of Community Development;
Bob Herrick, Assistant City Attorney;
Gary Johnson, City Engineer; and
Sue Devlin, Recording Secretary
PLEDGE OF ALLEGIANCE
IN RE: CONTINUED HEARING
GENERAL PLAN AMENDMENT 1-89 "B", TENTATIVE TRACT MAP 13901,
ZONE CHANGE 1068-89, CONDITIONAL USE PERMIT 1589-89,
ADMINISTRATIVE ADJUSTMENT 89-23, AND ENVIRONMENTAL IMPACT
REPORT 1143 - BURNETT/EHLINE DEVELOPMENT COMPANY:
The applicant is proposing a General Plan Amendment from
open space and low density residential to medium density
residential and local commercial. The applicant is also
proposing a Zone Change from R-1-7 (Single Family
Residential minimum lot 7,000 square feet) to PC (Planned
Community), and C-1 (Local Commercial) and a Conditional Use
Permit to allow the creation of 180 single family lots
without direct street frontage. Further requested is a
Tentative Tract Map to allow the creation of 180 single
family lots and two commercial parcels; and an
Administrative Adjustment to allow a reduction in parking
stall length and width permitting utilization of uniform
parking stalls throughout the commercial portion of the
project.
The site is comprised of 25 parcels totalling 37.1 acres and
is located along Santiago Creek between Tustin and
Cambridge. Included in the total acreage are 22 lots
located at the northeastern terminus of Rosewood Avenue.
NOTE: Environmental Impact Report 1143 has been prepared
for this project.
(This item has been continued from the Planning Commission
Meetings of August 21 and September 18, 1989.)
Planning Commission Minutes
October 9, 1989 - Page 2
This item was brought before the Planning Commission Meeting
of August 21. A number of. questions were raised and a study
session was held on September 11 to ask the questions of the
developer. The developer then came back to the meeting of
September 18 in order to give the Commission an idea of how
much time it would take them to answer those questions. The
applicant is at this meeting to answer and respond to said
questions.
Chairman Bosch discussed the Commission's procedure for the
public hearing. At the previous public hearing, this item
was closed after receiving public testimony. Commission
voted on how they wished to proceed.
Moved by Commissioner Greek, seconded by Commissioner
Master, that the Planning Commission re-open the public
hearing.
AYES: Commissioners Bosch, Greek, Master, Scott
NOES: None
ABSENT: Commissioner Hart MOTION CARRIED
The Commission also wished to address each question
contained in the packet, "Responses to Planning
Commissioners Questions Regarding the Villa Santiago Project
dated September 22, 1989."
The public hearing was opened
Applicant
Lynn Burnett, Principal with Burnett/Ehline Development
Company, 2050 South Santa Cruz, #100, Anaheim, stated there
were three primary changes to the development plan since the
August 21 presentation. They are an increase in minimum lot
size, a re-configuration of the LaVeta right-of-way and bike
trail, and a revision to the commercial parking plan. With
respect to lot size, minimum lot size has been increased to
4,000 square feet. Their largest lot is now 6,600 square
feet with an average lot being 4,400 square feet. He
pointed out if the land given up for the LaVeta extension
and the greenbelt were to be included in their calculations,
their average lot size would be nearly 6,000 square feet.
Concerning the LaVeta right-of-way, it has been modified to
increase the landscape area along LaVeta contiguous to the
residential area and the bike/pedestrian trail has been
integrated into the plan. Parking for the commercial retail
center has been reduced by 18 stalls, from 523 to 505. The
project still, however, maintains a surplus of 62 stalls in
excess of City requirements. Representatives of most of the
planning disciplines were present to answer technical
questions from the Commissioners.
Planning Commission Minutes
October 9, 1989 - Page 3
Questions & Answers
SITE PLAN:
Q.l. What is the FAR for each parcel?
Commissioner Greek's concern about the FAR is .77. In the
development plan the houses are listed from 1800 to 3100, so
the range is not really .77; it's something different.
Mr. Burnett responded .77 would be the extreme case; it
would apply to the largest home of 3100 square feet. Their
average home size is 2350 square feet, including the garage.
Q.2. What is the average size of the recreational
greenbelt areas for similar density projects?
Commissioner Scott questioned "not within the vicinity, but
within the City of Orange." They were only addressing the
proximity of this development. How does this compare to
what has been approved in East Orange? He did not feel
comfortable with the answer he received.
Mr. Burnett referred the question to staff. Staff did not
have available other recent developments in the City.
Commissioner Scott wanted to know if this were comparable or
not.
Q.3. It appears that the narrow parcels do not have
sufficient width for the double wide driveways
proposed, especially on the cul-de-sac lots.
Mr. Burnett said that is one of the areas they have made
substantial changes to the planned configuration. With the
increase in lot size, they have achieved a better balance
between lot sizes from the larger to the smaller. They have
achieved a better average. They have taken 17 to 18 feet
out of the commercial section; extended that boundary
eastward and added that additional footage into the
residential component.
Commissioner Greek asked for the dimensions on Figure 5,
Page 8, (residential development on the revised plan).
Rich Nolan, land planner with F.M.A., responded to the
question. The minimum is 42 foot width. It was intended to
show what the Z lot detail would be; how you create a Z lot
on a typical straight street. It was not intended to show a
typical layout of landscaping or driveways. He explained
there would be approximately 20 feet of landscaping, 20-22
feet of driveway and 1-2 f eet of some type of planter or
concrete.
Planning Commission Minutes
October 9, 1989 - Page 4
Commissioner Greek was trying to determine adequate parking
for the street, and whether or not it was going to work.
Mr. Nolan stated relative to the parking they calculated
what they felt realistically they could get for parking on
the street, and that was dimensioning off the amount of curb
along the interior streets and reduced it by a great deal.
The scenario has worked in other presentations.
Chairman Bosch asked what the actual length of parking space
would be between the driveways. What size did they use to
calculate the on street parking mentioned in other answers?
Mr. Nolan responded 20 feet per car.
Chairman Bosch asked if that included the apron of the
driveway in the 20 feet per car for on street parking?
Mr. Nolan said they did not get down to site planning for
individual lots. He believes 22 feet is a very liberal
driveway width.
Chairman Bosch asked if there was on street parking or not?
(Yes). What is the dimension of space between the driveways
that is usable for parking?
Mr. Nolan calculated it as 20 feet. They did not take 20
feet per lot as a parking stall. They did not show that
there would be 180 guest parking stalls on street.
Commissioner Scott said the standard driveway for a two car
garage is 16 feet, and explained the calculations as he
interpreted the plan.
Mr. Burnett said
plot houses. It
criteria. In th
feet. A parking
feet. They used
street parking.
this plan was not an attempt to precisely
was an effort to come up with planning
e majority of instances they will have 20
stall can vary in length from 17 to 20
some rules of thumb in calculating on
Commissioner Scott referred to the applicant's answer to
Question 3. In looking at the revised plan, Lot 176 only
has a 15 foot opening on it; 179 has 20 feet -- under the
dimensions for a normal 22 foot driveway. It will have to
encroach on the adjoining property owner.
Q.4. Why was no guest parking provided?
Mr. Burnett was not sure they had a calculation for the
anticipated number of on street parking stalls provided.
They could address it if it is a concern. In the majority
Planning Commission Minutes
October 9, 1989 - Page 5
of instances, there is ample room in front of the residences
for at least one parking stall. In some instances, it is
possible that on street parking may not be contained
strictly within the lot lines of the residences, but that is
a situation common throughout the City.
Q.5. What is the impact of fire hydrants to on street
parking?
Mr. Burnett said it was part of the same equation. They
will make an effort to position the fire hydrants in a
manner that will not take up a parking stall, but they did
not have the exact impact of that yet.
Commissioner Greek noted the 300 street parking spaces and
asked for Mr. Burnett's confirmation. (He stipulated to
that.)
Q.6. The provisions of Chapter 17.67 need to be fully
addressed.
Commissioner Scott wanted staff to respond to the
applicant's response -- was it adequately addressed?
Mr. Godlewski responded staff has not gone through the
response to questions in great detail and prepared a
response to every one. He will review it at this time and
give them a response in a few minutes. There was not a
great deal of time to go over the questions before
transmitting them to the Commission.
Q.7. The proposed lot sizes conflict with the East Orange
General Plan for low and medium density.
Chairman Bosch said the first paragraph indicates that if
the proposed development plan is not approved, the owner of
the property will be effectively deprived of the right to
develop the property. Isn't it true that the applicant has
current zoning applied to the property?
Mr. Burnett responded yes. The property is currently zoned
R-1-7,000 and has been zoned that designation since 1956.
Additionally, the General Plan is approved and in place,
allowing up to six dwelling units per acre.
Chairman Bosch was interested in the person's logic, given
that the applicant has a General Plan and zoning on the site
that this plan before the Commission today is the only one
that necessarily would allow them to develop the property.
The E.I.R. addresses several alternatives that appear to be
available.
Planning Commission Minutes
October 9, 1989 - Page 6
The response was prepared by Maureen Hardy, 14 Mountain
View, Irvine. She meant that economically due to the
channel improvements and LaVeta, this is the plan that is
necessary to take care of all of the infrastructure
improvements to develop the property. The present R-1-7
requiring 7,000 square foot lots when you plot them out with
the odd configuration, even without LaVeta, but the creek
running through it, makes for very few lots. She was not
intending to reply to the legal status of the current right
to develop under existing zoning.
Q.8. Justify the strip zoning for commercial on Tustin.
Commissioner Scott said when you look both north and south
of the project area on Tustin it is residential. How do you
justify re-zoning this to commercial?
Mr. Burnett said that was corre
south is the apartment project on
to the north, but if you go
established as commercial. The
prevalent up and down Tustin.
instances of some residential -
residential and higher density.
~t. Immediately north and
Fairway, mobile home park
beyond that, Tustin is
commercial zoning is more
It is true there are spot
- primarily multi-f amily
Commissioner Greek wanted justification for the depth
relating to the intensity of commercial use.
Mr. Burnett said the depth was determined primarily as a
result of the layout of the commercial center itself. If
they are too deep, the commercial viability of the project
is cut down; if it is too shallow, then there isn't enough
commercial to support it.
Q.6. Chapter 17.67 - Staff review
Mr. Godlewski reviewed the application against the
requirements when the applicant first came in to make their
proposal. What is stated is correct. The applicant has met
all the provisions of the Planned Community District. When
the Commission was asking the question, the tone of the
question was whether it meant the requirements of the
Planned Unit Development. That is not what they are
applying for. They are applying for a Planned Community,
which is different. In a Planned Unit Development there is
a trade off for open space and clustering of units. In the
Planned Community you basically write your own zoning
ordinance and this is what the applicant has done.
Commissioner Greek asked for verification of Item D, Page 3
-- density and units per acre. He would like to see a table
of how these things fit.
Planning Commission Minutes
October 9, 1989 - Page 7
Mr. Godlewski said the representation of densities is not
required by code. Staff looks to the description in the
definition to describe what it is they are measuring.
Mr. Burnett responded the acreage dimensions have shifted
recently. They took two tenths of an acre from the
commercial and integrated that into the residential. Figure
6, Page 9 of the development plan are the current acreages.
The density number has been rounded slightly. It's 6.9
dwelling units per acre. The PC is more accurate.
Commissioner Greek asked about the statement on Page 3 of
the responses. What are the public facilities?
Mr. Burnett said the reference to public facilities were the
greenbelt areas which cover 1.5 acres. Other public
amenities have to do with the bike trail and pedestrian
path.
Commissioner Greek asked when will a decision be made
whether or not LaVeta is part of the Master Plan of
Highways?
Mr. Johnson responded LaVeta was considered a special study
street and was not included in the circulation element.
This project was meant to be the study vehicle for that
special study street. The road is shown as being an
arterial and its implementation will require an amendment to
the Master Plan of Arterial Highways and the circulation
element. The County is in accord with that and would react
favorably.
Q9. Evaluate the impacts of the 12 foot high wall on the
mobile home park.
Mr. Burnett referred to their illustration on Page 28 of the
PC. It is a condition that was brought about by the grade
differential between the existing grade of the mobile home
park near Tustin and the actual street grade of Tustin. As
the property line continues westward from Tustin, that
condition continues. The grade falls off; however, there is
a situation right at Tustin where the grade differential is
approximately 12 feet. The steps they have taken to
mitigate that condition to soften it by building a stepped
wall on the mobile home side. It is 5 to 8 feet in height
with landscaping. The intent is to get some height and
landscaping, as well as a cascading plant material to soften
it. Beyond that is the actual property line wall, which
would be a 6 foot wall. On the other side is additional
tree planting.
Commissioner Scott asked about the illustration on Page 28
-- where is the property line?
Planning Commission Minutes
October 9, 1989 - Page 8
Mr. Burnett said their property line is the lower wall. It
is intended to be 5 to 8 feet dealing with the varying
conditions.
Q.10. The buffering of the site from the adjacent
residence may be inadequate.
Commissioner Greek does not believe effort has been done.
Q.11. Submit emergency access gate details.
No comment.
Q.12. Concern with
should justi
standard 20 f
the 18 foot garage setback.
fy the reduced driveway length
eet.
Commissioner Scott said this has been approved on some
developments in the past, but it has been criticized as far
as the length less than 20 feet. The applicant's response
was because of the automatic door opener on the garage
doors, there was not a need to be concerned with the door
opening. This has been a concern in East Orange. Is it
adequately responded to?
Commissioner Greek was also concerned and his recommendation
would be not to have 18 foot driveways. It should be a 20
foot driveway.
Mr. Burnett understood most of the criticism on the shorter
driveways in East Orange were because they were much less
than 18 feet. Eighteen feet is a fairly typical car length.
In addition, they will provide a sectional roll up door.
Q.13. Give the density for each phase of development, and
for each separate parcel under different ownership,
excluding the area for streets from the calculation.
Commissioner Greek did not feel the question was answered.
Mr. Burnett stated this was a difficult question. The
concept of the project is a totally planned environment.
It's not envisioned that portions of the development would
be Master Planned and sold off. This is intended to act as
a whole. The density (shown on the site plan) is on the
residential and is evenly spread across the site. All
infrastructure work will be completed at the same time.
Commissioner Greek wanted to get a feeling of the overall
density in the existing golf course units, then the Rosewood
tract and the County parcel to end up with 180 units. The
biggest problem is the possibility of the commercial
~licant
rom the
Planning Commission Minutes
October 9, 1989 - Page 9
property being sold and the rest sitting there forever. A
condition needs to be written to tie the fact nothing can be
started until ownership is in one title.
Mr. Godlewski was not sure if there needed to be a
condition. The applicant would need to implement the tract
map as proposed, and any modification to that would be a
substantial modification to everything being requested.
Mr. Burnett's
presented. If
be a signific~
plan. There
infrastructure
would make it
rapid basis.
intent is to deal with the entire plan as
one piece were not to be involved, that would
ant enough change to come back and revamp the
is approximately 17 million dollars worth of
involved and would be put in initially, which
important to develop the site on a fairly
Q.14. Clarify the range of lot sizes, the minimum average
lot size and address the lots that do not conform
with the regulations spelled out in the proposed
Planning Commission text.
Mr. Godlewski confirmed that statement. All the lots meet
the minimum 4,000 square foot lot size.
Commissioner Scott said because of the problem with the
small lots in East Orange, it was proposed that small lots
be dispersed throughout a subdivision and be limited to 30~
of the total lots. An amendment to the East Orange
development standards is being processed and now this
project will go against those standards.
Mr. Godlewski responded after looking at the original
tentative map, staff found a number of lots that did not
meet the minimum 4,000 square foot dimension. There was
some discussion of East Orange, but the primary concern was
that their proposed tentative map did not match what the
requirements were in the PC zone booklet. Staff did not
address the issue of the East Orange consistency.
Chairman Bosch noted the applicant had an exhibit A by the
Keith Companies that showed lot sizes and it seemed the
smaller lot sizes were on one side and the larger on the
other.
Mr. Burnett said there
earlier plan and the
minimum lot size is
better balance betwee
of factors involved in
Orange nor found in
some economic factors
infrastructure costs.
were some inconsistencies between the
PC, but have been resolved. The
4,000 square feet. They achieved a
n large and small. There are a number
their site that are not found in East
other projects in Orange. There are
unique to this project; namely, the
Planning Commission Minutes
October 9, 1989 - Page 10
Q.15. Incorporate the addendum onto the text (referring to
the development plan).
Staff confirmed the changes were made and incorporated into
the text.
Q.16. What is the affect of the Rosewood cul-de-sac on the
surrounding neighborhood?
Commissioner Greek recommended changing it to a standard
cul-de-sac because there is another cul-de-sac to the north
that serves the same three houses.
Mr. Burnett has met with Traffic Engineering. The looked at
the proposal for the termination of Rosewood and have agreed
in concept what is laid out. It is a short distance there.
The impact to the existing neighborhood is that traffic will
be significantly diminished.
Q.17. The commercial parking is in excess. Why not
incorporate this excess space into the greenbelt?
Chairman Bosch understood the excess space has been
incorporated into increasing the lot sizes rather than to
the greenbelt.
Mr. Burnett said they re-balanced it and some did go into
the greenbelt area. The majority of it went into the
residential land area. He pointed out they diminished the
number of parking stalls by 18. There is still a surplus of
parking in the commercial area. Reduction of the greenbelt
area has to do with the re-defining of the LaVeta
right-of-way and area that was previously in the
right-of-way. The net change is that there is additional
landscaping on site that comes into play with the
modification of the landscape area contiguous to the
residential component along LaVeta. It has been increased
by six feet. It is not being counted in the greenbelt area.
Q.18. With the greenbelt extending past the commercial
portion of the project, the bike lane can be taken
off the roadway.
Chairman Bosch understood the bike lane has been taken off
the roadway, but does not extend past the commercial portion
of the site, nor does the greenbelt extend past a portion of
the site.
Mr. Burnett responded that was correct.
Q.19. The restaurant parking lot impacts the adjacent
residences. Justify the proposed mitigation
measures_
Planning Commission Minutes
October 9, 1989 - Page 11
Commissioner Greek thought the car lights would shine into
the residences because they are raised above it. The
response is not really adequate.
Chairman Bosch said there appears to be a 5.4 foot grade
differential with a property line wall. The wall is going
to be at the lower elevation of the residential lots and the
lights would shine over the top.
Mr. Burnett would be happy to look at that further. It
would be possible to re-grade that and go with a combination
retaining wall in an effort to accomplish that.
LA VETA EXTENSION:
Questions 1, 2, 3 and 9 were being responded to by Bernie
Dennis, City Traffic Engineer:
Mr. Dennis answered the question - the benefits vs. the
consequences of the LaVeta extension on the adjacent major
roadways. The comparison is made in the recently adopted
circulation element of the City's General Plan and is
included a graphic in the project E.I.R.. As a shift in the
area circulation occurs at the LaVeta extension, Fairhaven
has also been included in the attached exhibit 1 comparing
both and providing capacity ratios as extracted from the
circulation element and tabulated for this report. It gives
the comparison of traffic volumes on street segments on
Chapman, LaVeta, Fairhaven, Cambridge and Tustin. It gives
the projected daily average traffic volume without the
extension and with the extension. It also gives the volume
capacity ratio. It should be noted is the traffic demand is
a function of approved land use and is a constant. The
increase/decrease of traffic volumes over the street system,
whether it be with or without LaVeta, is actually a
balancing of total traffic demand. The volume capacity
ratio is a measurement of the street's functional ability to
accommodate a given traffic demand. This is expressed in a
level of service, with level of service A being the best and
level of service F is the least desirable. The street would
be at capacity at this level. Using exhibit 1, certain
relationships can be determined for impacts. With or
without the LaVeta extension, Chapman will operate at or
near capacity. A similar relationship can be made comparing
three streets: Fairhaven, LaVeta and Cambridge. The demand
on Fairhaven and Cambridge exceeds the mitigatable capacity
at several street segments without the LaVeta extension.
With the LaVeta extension, subsequently an additional
street, the balancing of the east/west demand tends to
occur. The balancing is a redistribution of traffic. There
is very little change in traffic volumes on Tustin. There
is a slight increase in demand. Regarding the two freeways,
Planning Commission Minutes
October 9, 1989 - Page 12
the extension of LaVeta has virtually no effect on the
freeways. Another consideration is what will happen to the
streets in the area that were not addressed by the
circulation element; specifically, Fairway and Palmyra.
Without an arterial existing between Chapman and Fairhaven,
these two streets in combination are providing the east/west
capacity between Cambridge and Tustin. There is very little
that can be done to mitigate the excessive traffic other
than some type of diversion strategy.
Commissioner Master stated with the amount of traffic
anticipated from the analysis on LaVeta, are there
sufficient mitigating measures that will meet the City's
standards for noise and the residents?
Mr. Dennis responded the Commission's concern was the impact
to residences on Rosewood and Fairway with regard to having
a street adjacent to both their front and rear yards.
Staff's response is although there are hundreds of
residences in the City of Orange that have a back-on,
front-on road condition, in most cases both the dwelling
units and roads were in place at the time of purchase. They
were not retrofitted. In that condition, there are two
factors from a traffic perspective that require specific
consideration: noise and light glare. Regarding noise,
street grade, elevation, traffic composition and traffic
duration (the period of time the traffic occurs) are the
four traffic factors that must be considered and effectively
mitigate noise impacts to adjacent residents. The other
factor is ligh t glare. In respect to on-site improvements
involving commercial and office/industrial development
adjacent to residential land uses, the configuration of the
parking area, security lighting and the building material
reflection are prime consideration in mitigating that
problem.
Commissioner Master asked what was going to be done? Is
there a proposed plan for potential mitigation of impacts on
the adjacent residences?
Mr. Burnett referred to Page 14 of the PC, diagram 11.
Regarding the Rosewood section, there is a grade
differential of 4 to 5 feet. The LaVeta side is the lower
side. They have created a 20 foot buffer, which will be
heavily landscaped, sloping up to a wall that would be on
the property line. The design of that wall is intended to
mitigate sound. Final height would be subject to a further
sound attenuation study and recommendation by a sound
engineer. East of Rosewood, they have created a 1.4 acre
greenbelt area. It averages 70 to 80 feet from the property
line to the street. It is to be landscaped and bermed. In
addition, the residents in existing homes would have the
option to choose a fence material suitable to their
particular situation.
Planning Commission Minutes
October 9, 1989 - Page 13
Commissioner Master asked if the applicant were going to
meet City standards as far as sound level?
Mr. Burnett said these are mitigating measures as a result
of the study that was done through the E.I.R. process.
These measures would satisfy the requirements and will meet
City standards. The E.I.R. indicates there is a bit of a
sound problem already in the Rosewood area as a result of
the freeway extension. The indication is that after the
project is constructed and a sound wall put in place, the
sound level would be reduced over its present level. If
needed, they will increase landscaping or the sound wall.
Mr. Godlewski pointed out there are a couple of places where
noise is addressed in the documents before the Commission.
It is addressed in the mitigation measures attached to the
project in the E.I.R. report, as stated by the applicant.
It is also addressed on Pages 11 and 29 of the Statement of
Overriding Considerations. It discusses the aspects of
noise that take place because of the environmental factors
of the freeways and other noise generating sources outside
the project's ability to control. The statement says we
recognize this noise environment does exist; the applicant
will do whatever he can to mitigate this. Additional
studies will be made by acoustical analysis prior to
issuance of building permits. It will also be reviewed by
the Design Review Board.
Mr. Dennis responded to the question of submitting a
signalization plan for the intersection of LaVeta at
Cambridge and Tustin. The construction plans and
specifications for the modification of the traffic signal on
Tustin and LaVeta, and the installation of the traffic
signals and safety lighting at Cambridge and LaVeta East
have not been prepared as both of these construction
projects are dependent upon this particular project. He
provided a conceptual overview of how the signals would
work. A conceptual channelization plan was attached,
exhibit 2. Rosewood and Cambridge would not be restricted
to right turns in or out.
Commissioner Scott asked if this development would be
similar to a recent development -- Home Depot -- on Katella
where they were required to modify the signal at Katella and
Glassell, as well as install the signal at their main
entrance at their cost? If the same, would the developer
front the cost of the modification to Tustin and LaVeta?
Mr. Dennis responded that was correct; also install the
signal at Cambridge and LaVeta East. And also with the
revised plan, those mitigation measures that would be
required for the bike crossing between Tustin and Cambridge.
Planning Commission Minutes
October 9, 1989 - Page 14
Commissioner Scott stated it should be listed as a
condition.
Mr. Dennis said the traffic signal at Cambridge and LaVeta
West is related to the LaVeta West improvement project.
It's included in the Capital Improvement Program, which is
scheduled for installation in 1990-1993. It is a stand
alone project.
Q.4. Evaluate the adequacy of the proposed internal
circulation svstem.
Commissioner Scott asked if LaVeta should be extended
between Cambridge and Tustin and the proximity of the
residential homes, would it be posted for no truck traffic?
Mr. Dennis stated yes. LaVeta, from City limit to City
limit, or at least from Glassell to the East City limit
(i.e., Esplanade) is not designed nor would truck traffic be
encouraged. It would be posted.
Commissioner Greek questioned the applicant's response. The
statement should have a comment and staff should response
with their evaluation.
Mr. Godlewski responded in terms of the adequacy of turning
radius and serviceability, that was reviewed by City
departments and found to be adequate. There is some
discussion in the E.I.R. as to the adequacy of the street
internal circulation, but he could not recall the details.
Mr. Johnson stated the circulation with regard to the
residences is adequate from the standpoint of emergency and
vehicular circulation. The street widths were adequate.
Staff felt they could live with the street configuration.
Q.5. Refers to the connection of the existing LaVeta east
of Tustin and then refers to correlate with the new
creek/culvert alignment.
No c omme nt .
Q.6&7 How is visitor access handled? What are the queing
and parking availability at the entrance gates?
No comment.
Q.8. Where are the bus turn-out locations? RE: OCTD
comments.
Chairman Bosch noted the revised plans still does not show a
bus turn-out lane.
Planning Commission Minutes
October 9, 1989 - Page 15
Mr. Burnett has
the process of
of the turn-ou t
this point.
had conversation with OCTD and they are in
specifying where the location and dimension
would be. That has not been finalized at
Mr. Dennis responded that regardless of what OCTD decides,
the bus bay, if it occurs, will go on the southwest corner.
There is another problem of putting it on the northwest
because of the bridge structure. He explained the
dimensions and criteria for the bus bay.
The response given is incorrect; it would be the southwest
corner, rather than the northwest.
SANTIAGO CREEK:
Q.1. Submit security details for underground culverts.
Commissioner Greek asked Mr. Johnson if he agreed with the
applicant's statement.
Mr. Johnson believes if the Flood Control District is going
to take it over, they will be concerned with the security of
the facility because they are responsible for anything that
happens within that right-of-way. If they're saying the
entrance can be secured in a manner that doesn't require an
obstruction to the flow of water, it appears they are
willing to take that over.
Q.2. How will debris build-up be handled?
Chairman Bosch asked how the debris catching on the security
fences would be overcome?
Mr. Johnson said the security fences would not cross the
channel. Debris would not hang up on anything until it came
out of the culvert at the end. At that point there would be
some type of trash rack that would give with the pressure of
the water or trash in a manner that would not create a back
up at that location either.
Chairman Bosch asked how the Flood Control District get
security to prevent unauthorized access to the culvert?
Someone could walk downstream into the culvert.
Mr. Johnson said they could control it within a given
distance both upstream and downstream, but if someone wanted
to come in from Chapman at the park and walk down 1/2 mile,
they will be able to gain access. At some point in time,
the County will control the entire right-of-way along the
creek, but not with the first phase of development.
Planning Commission Minutes
October 9, 1989 - Page 16
Q.3. Evaluate the up and downstream impacts.
(Also included were Q. 4 - 8)
Chairman Bosch, with the Commission's concurrence, would
like a full presentation on the next several questions which
relate to one another.
Carl Nelson, Keith Engineering, in response to Q.3.,
hydraulically, the water will enter the Tustin bridge much
as it does today. The underground conduit going away from
Tustin Avenue will have its grade line devised in a way that
there will not create an upstream back water. The natural
flow, as it would be upstream, would not be disturbed. The
stream line pier walls will be extensions of the existing
Tustin bridge pier walls, which are now vertical. Debris
will not catch and hold. The invert (or bottom of the
channel) will be a control point and will not create
upstream hydraulic problems. The water will look the same.
Downstream they will achieve the same effect with the
transition from the underground conduit to the open. There
will be some energy dissipation in the transition returning
the flow as close to the natural velocity as possible. The
project is designed not to create either an upstream or
downstream problem. It is being designed for a flow rate of
12,000 cubic feet per second.
Commissioner Master noted the transition takes place some
distance west of Cambridge.
Mr. Nelson said the underground conduit will be under
LaVeta. The conduit will be carried downstream a short
distance partially through the City property because at the
location where the new conduit crosses Cambridge, it does
not reach the existing channel. That extension is simply to
extend down to reach the existing waterway. As a biproduct
of the extension, the City property and it's frontage on
Cambridge, can then be utilized for whatever purpose the
City determines in the future.
Commissioner Greek said it looked like the upstream phase of
the Flood Control right-of-way is next to the buildings.
Mr. Johnson thought the buildings were fairly close, but the
intent is not to encroach. There are some improvements on
that side and they would have to tie the southerly side of
the bridge abutment into the channel protection that exists
along the south side.
Mr. Nelson said the boundary line shown there would be the
existing channel right-of-way upstream. There is rip rap on
both sides of the channel as you approach the Tustin bridge.
That rip rap will be modified somewhat to channelize the
Planning Commission Minutes
October 9, 1989 - Page 17
flow into the conduit as it goes through the Tustin bridge.
There will be two vents at the Tustin bridge that will not
be needed. There will be no construction outside of the
right-of-way. The vents would be sealed off to meet the
City's approval.
Commissioner Greek asked if the City Engineer has reviewed
this and is the City willing to accept the relocation of the
channel into the City property on the west side of
Cambridge?
Mr. Johnson thought the question of how far down stream the
Flood Control accepts jurisdiction is an issue. The intent
is to get the flow of water back to its original state by
using a hydraulic jump at the outlet structure. There may
be some additional mechanical means used to further retard
the flow and slow down the water. All of the outlet
structure should be part of the Flood Control District
jurisdiction rather than leaving the City with a problem of
maintenance or erosion control problems in the future.
Commissioner Greek asked if there had been staff discussion
on whether or not this was an acceptable location or
acceptable construction within the City property?
Mr. Johnson stated staff's concern was that area or an equal
area to the south is encumbered by the channel. It appears
the City is reclaiming some of the land for usable property
by allowing that area to be used for the outlet structure.
That's a good trade off assuming the City does not have any
of the on-going maintenance problems associated with the
change in flow characteristic.
Mr. Nelson said the intent would be to convey to the Flood
Control District an easement over the entire construction,
including whatever length of underground conduit is to be
built and including the transition and rip rap to the point
where it rejoins the natural channel. There is no intent to
leave part of the structure with the City. The existing
waterway, where it comes out of the Cambridge bridge, is
much wider than the concrete conduit. So there would be a
reclamation of land on the City property.
Chairman Bosch understood there was potential liability
ramifications that occur when one reconstructs a waterway
outside of its natural path that doesn't occur when you
reconstruct it within the natural path. How will the City
be able to avoid the liability incurred from from that
outcome ?
Mr. Nelson said the general rule is that you come to the
rejoining of the natural stream to bring the water into the
Planning Commission Minutes
October 9, 1989 - Page 18
natural stream in an alignment and of a velocity that is
close to the condition that it would have gone there in the
first place.
Mr. Herrick addressed the legal aspects. He prepared a
memorandum provided to the Commission addressing those
issues. With respect to flood control, there is a new law
that has been generated by the Supreme Court recently which
cuts back on the old rule, which was strict liability in the
event a flood control structure fails to perform up to its
design capacity. There is now a rule of reason that appears
to have been laid down by the Supreme Court and that reason
requires a balancing of the public benefit from the Flood
Control project against private harm that could occur in the
event of a failure. The rationale for that analysis is laid
out in detail. The problem one has is the Supreme Court
case specifically applied that rule of reason to cases in
which the natural channel is not changed. There is a Court
of Appeals case that has extended that to cases in which the
channel is changed, but it is not known at this time whether
the Supreme Court will agree. There is a possibility that a
rule of strict liability may apply. The best protection is
to do a careful analysis and rely upon qualified experts to
make a determination that you are acting reasonably. In the
event there were a f ailure of this flood control structure,
there is no question the City will be a named party.
Mr. Nelson commented on the reasonableness. If the creek
were being lined with concrete in its existing location,
there would still be the problem of transitioning back to
the natural downstream from Cambridge. The engineering
approach is to bring the creek into the shape, size, depth
and velocity of flow that it would be in the prior
condition. There is a National policy which evolves from
the Federal Flood Insurance Program providing for a 100 year
flood. The Corps of Engineers will be involved in the
review and the Orange County Flood Control District, has as
its standards for a large creek the 100 year flood and they
have already acknowledged their willingness to accept the
project and conveyance to them when improved to their
standards. The flow rate is something that will only be
required until the Corps finishes more improvements upstream
at the gravel pits, which when finished, will be a form of
flood control reservoir that will reduce the flow rate to
just a little more than one-third that is being designed
for. The tentative schedule for completing that gravel pit
modification to reduce the flow would be 1992 or 1993.
Mr. Herrick clarified there are two separate issues of
liability with respect to design: Inverse condemnation
(damage to property) because of use by the public; and
design negligence.
Planning Commission Minutes
October 9, 1989 - Page 19
Mr. Nelson stated on Question 21 there is a list of examples
of structures of this type that have been in operation for a
period of time. Question 4 has been touched on regarding
the impact at the culvert interface.
Question 5, the Flood Control District has already indicated
their concurrence in accepting the improvements. He was
confident the Flood Control District would require the Corps
approval. There is a Federal law requiring a Section 404
permit be obtained from the Corps of Engineers before
getting permission to build.
Question 6, as to the
any of the construction
Modification of the ri
would be satisfied that
drain into the creek,
originally designed.
MWD facility, they do not anticipate
directly impacting the MWD facility.
_~ rap would have to be such that they
their facility, which is intended to
will continue to function as it was
Commissioner Scott believed MWD has the relief in the creek.
Will the design take care of that? (Yes.)
Question 7, the main feeder line, which would blow off
underneath the creek, they do not anticipate doing anything
more than improving their protection. That would require
their approval before proceeding in their right-of-way.
Question 8 on the transition structure details, the details
would be in the final plan specifications. They do not have
in the conduit a large change in velocity. That's the
principle concern of going through a transition. He
explained the critical velocity of the transition.
Question 9, issue of ownership, the proponents will be the
owners of the property. There is Flood Control right-of-way
upstream and downstream and there is City right-of-way and
MWD right-of-way; all will require permission for the future
operation and maintenance.
Question 10, evaluating the impact of the culvert on the
Tustin and Cambridge bridges, who will pay for the
modifications -- the entire project of the flood conduit
will be designed as a single construction project. There
would be no structural modifications to the Tustin bridge.
At the Cambridge bridge it would be necessary after the
completion of the new conduit to remove the old Cambridge
structure. All construction would be at the cost of the
developer.
Question 11 is regarding impacts to the creek downstream,
which has been discussed. No one is requiring larger than a
100 year flood to be accommodated. Within the next three
years, as soon as the development could be occupied, the
Corps of Engineers will have a reduction in the flow rate.
Planning Commission Minutes
October 9, 1989 - Page 20
Chairman Bosch said 'the written response indicates that
under any design there would be more than 12,000 cfs
regardless of the reduction. He had concern with the
proposed grading and elevations shown on the tentative tract
map.
Mr. Nelson said the answer was not intended to say the whole
creek could overflow into LaVeta. If there is a minor
overflow or if the water got higher, the conduit would be
designed for open channel flow. The water surface inside
the conduit would be below the ceiling (soffit). If there
were more flow and the water should seal and be a pressure
condition, it's like a sewer that gets too full. Water can
back flow through the entries in LaVeta or at the Tustin
bridge.
Chairman Bosch asked at what cfs would it overflow and how
much would the LaVeta design accommodate?
Mr. Nelson did not have a number, but talked about a flow
that would exceed the 100 year flood. He gave a brief
history of the flood information.
Q.12. Evaluate the impact to Tustin and Cambridge traffic
during bridge construction.
Mr. Nelson claimed there would be no impact on traffic
except on the westerly side of Tustin when the railings
would be removed and the interface between the parking and
the bridge and new curbs, and the intersection of LaVeta
would be constructed. On Cambridge there would have to be a
detour during the construction of the conduit through
LaVeta. There would need to be a staged detour for removal
of the Cam bridge structure. Cambridge would not be closed,
but transitioned. Plans would be submitted to the City for
review.
Q.13. Show how LaVeta is designed to handle run-off and
creek overflows.
Mr. Nelson said the run-off would be minor and touched on
that earlier. Some excess could flow down LaVeta.
Q.14. Evaluate what the impact of increased run-off in
east Orange due to new construction has on the
project.
Mr. Nelson said east Orange was small compared to the
overall watershed. Most of the watershed for Santiago Creek
is within the Cleveland National Forest. There would not be
an increase on the major part of the watershed. The design
flow rate for the conduit will be 4300 cfs. There will be a
Planning Commission Minutes
October 9, 1989 - Page 21
treme ndous safety f actor in 1993. The Flood Control
District, City and Corps of Engineers tend to look, within
an area like Orange County and have for many years, every
bit of land that is not under some kind of government
ownership, would develop in accordance with the General Plan
of the jurisdiction that has control. The Sphere of
Influence for the City of Orange goes out to the entire
tributary watershed except for the National Forest.
Question 15, the SAVI line easement, has an interesting
history and Mr. Nelson explained it. The large concrete
pipe within the easement was converted to drainage so that
it would improve the drainage of City streets north of this
property.
Mr. Nelson summarized the liability for culverts; Orange
County Flood Control District will own and operate the
Santiago Culvert and will be named as first party.
Question 17, status of up and downstream creek improvements
-- the Santa Ana River federal project includes Santiago
Creek. The concept for the federal project is simply at the
gravel pits to put in a gated outlet such that the pits will
function like a flood control reservoir.
Q.18. What is the current Q required by OCFCD?
Chairman Bosch asked how the Q relates to the velocity and
how it is determined?
Mr. Nelson said calculations would be provided to back up
the plans; natural velocity upstream is 10 to 12 feet per
second.
Questions 19 and 20, after they accept the letter of
conveyance, OCFCD maintains it. They would take the
responsibility of fencing and maintenance a s they do
throughout the Flood Control Di strict.
Question 21, list of similar type underground conduits
given. He added only the Santa Ana Delhi channel is the
only one designed for a 100 year flood. The others were
designed in earlier years for a 25 year flood.
Question 22, is more of a geotechnical question, but he
summarized it by saying that the creek at this location is
permeable and it is illustrated by the fact that a short
ways upstream big pits have been dug to harvest the sand and
gravel. Subsurface flow tends to be vertical rather than
lateral in these conditions.
VILLA SANTIAGO:
Planning Commission Minutes
October 9, 1989 - Page 22
Q.23&24 What is the status of the 1603 permit and its
relation to the proposed land use; and how will the
net wetlands loss be mitigated?
Chairman Bosch read the response and stated in the Statement
of Overriding Considerations to the E.I.R. also included the
case that if it could not be found, that it would be a
measure that could not be mitigated.
No further comment.
Q.25. What is the phasing of the creek improvements and
what effect will it have on other City projects?
It indicates creek work not allowed to begin earlier than
March 15 nor completed later than November 15. Phased
construction does not appear feasible within the creek bed.
No further comment.
BIOLOGICAL IMPACTS:
Q.1.&2. What is the box size of the replacement trees? 15
gallon trees are too small for replacement trees.
Chairman Bosch asked what the affect was in the difference
of size between a 20 inch box and 15 gallon tree?
Mr. Burnett was not sure if he could answer that except to
say that 20 inch box trees were larger than 15 gallon trees.
Q.3.
Indicate on the plan where the specimen quality oak
and sycamore trees are located and the impact of
keeping them in their present locations.
They are shown on exhibit
Burnett said they make an
trees into the landscape.
AIR QUALITY:
9, Appendix H of the E.I.R. Mr.
effort to incorporate healthy
Q.1.&2. How will monitoring of grading operations be
accomplished; and what standards for particulate
emission will be used?
Chairman Bosch read the applicant's response. Is there a
requirement within the AQMD regulations for monitoring by an
independent testing laboratory retained by the developer
during continuous on-site conditions rather than the spot
check by AQMD?
Mr. Burnett was not familiar with one if there is.
No further comments on Air Quality questions.
Planning Commission Minutes
October 9, 1989 - Page 23
LANDFILL
Q.1. Clarify hauling quantities, haul routes, alternate
routes and number of trigs.
No comment.
Q.2. The amount of fill required appears greater than the
amount stated in the E.I.R. Resolve this
inconsistency.
Chairman Bosch asked which quantity was correct?
Mr. Burnett responded the later number is correct (the
lesser number). The current quantity is 250,000.
Q.3. A condition for the project specifies an increase of
fill over the culvert from 3' to 5'. Evaluate
impact of this increase for fil_1 amounts, hauling
operations and grading phasing.
Commissioner Greek asked which number is adequate?
Mr. Johnson thought the answer varied in certain locations.
He did not think the existing culvert was parallel with the
ground. Staff's concern was 3 to 5 feet was a ballpark
figure based on the need to give adequate cover to the
utilities.
Commissioner Greek felt if staff were going to require five
feet of fill over the culvert, that will require an
additional two feet of import over the whole tract. It
would be a substantial increase in import. This needs to be
clarified.
Mr. Johnson did not know if there was enough flexibility in
the grades of the culvert itself, but maybe the culvert
could be lowered in certain areas and still make the
structure work hydraulically. If that is the case, there
won't be any additional fill brought in. They will cut more
on the bottom of the culvert and filling more on the top so
it is a wash. He did not have any information that would
tell him one way or the other.
Eric Nielsen, Keith Engineering, clarified that the
condition originally came as a request from the Orange Water
Department with the assumption that the water line would be
placed on top of the culvert. Subsequent discussions with
the Water Department, after the original staff report was
prepared, indicated some alternative alignments for that
water line might be acceptable. Namely, placing the water
line adjacent to the box with adequate cover rather than
right over the top.
Planning Commission Minutes
October 9, 1989 - Page 24
Chairman Bosch asked how the other side of the development
would be served?
Mr. Nielsen said they would try to provide adequate cover or
special construction methods where a 5 foot cover couldn't
be achieved. They are willing to work with staff on the
details of that design. The sewer will have to run parallel
and then they will have to find a place where it is deep
enough to go underneath (probably under Cambridge).
Commissioner Greek said they had a staff report which
recommends a given condition and they don't have a staff
report not recommending that condition. If this gets
approved and if they use the staff conditions, the applicant
would have to put a 5 foot of cover on it. The quantities
are not correct if an additional 120 yards were to be put
on. Clarification was needed.
Mr. Johnson suggested changing the condition such that the
standard grades of the culvert must maintain the minimum
cover over the utilities.
Mr. Nielsen said it was their intent to keep the grading to
a minimum, which is the essence of the concern.
Chairman Bosch reiterated staff felt Condition 39 should be
modified to change it from the 5 foot minimum coverage to
some other wording.
Mr. Johnson responded some wording that would indicate the
minimum standard cover for utilities shall be maintained
over the box.
Q.4. What is the grading phasing plan for both the
commercial and residential portion of the project?
No comment.
Q.5. Conditions are needed which will enforce the grading
plan as approved by the Planning Commission.
Chairman Bosch asked if staff has had an opportunity to look
at that item? Are the standard provisions appropriate
protection for the City to enforce the grading plan?
Mr. Johnson said that any tract map that is filed and shows
certain grades, if there is a substantial deviation from
those grades, staff would bring it back or get the revision
approved.
Q.6. The
be
different
ding and
resolved?
parcel ownership m
hasinQ of the project.
affect the
ow will this
Chairman Bosch said this was answered before.
Planning Commission Minutes
October 9, 1989 - Page 25
Q.7. What other dust controls are available other than
AQMD requirements?
No comment.
Q.8. How will the Rosewood tract excavation and fill be
accomplished?
No comment.
Q.9. What is the extent of the old dump site?
Mr. Johnson thought the applicant's response was somewhat
misleading. The first time through, the dump was
reclamated. There was material excavated. The major
failure has occurred at the intersection of Eagle and
Rosewood and in the cul-de-sac area of Rosewood. The entire
area shown as a dash line would not require complete
rehabilitation. It will be necessary to provide a full-time
on site geologist technician who will review the grading and
make recommendations as to how far they go to get the bad
stuff out.
Mr. Burnett said their approach to this issue is a little
different than their predecessor's. Their solution is
simple -- pull it all out. They are prepared to go down 30
or 40 feet.
Gerald Nickel, G.A. Nickel & Associates, Geologist & Soils
Engineers in Tustin, 15621 Redhill Avenue. With respect to
the current investigation of the site they have additional
test pits and borings. The borings go to a depth of
approximately 55 feet. There are seven new borings. As a
result of the previous history of development and substance
in the area, there was a considerable amount of existing
information. They wanted to verify the findings as to the
quantity, depth and quality of the fill materials that were
present. The materials were also investigated as to extent
by way of photo investigations. They were able to prepare a
contour map which gave them a pretty good handle for their
own internal use. They were able to confirm by a backhoe
test the location of haul roads and the boundary of the pit
and slope angle. They were able to drill through the
landfill into natural ground. It is not necessary for
borings to go down 80 feet.
Q.11. Temporary grading and dust impacts may affect
adjacent residents resulting in a negative impact
to their quality of life. How will these impacts
be mitigated and how will adjacent residents be
compensated for a loss in life style?
Planning Commission Minutes
October 9, 1989 - Page 26
Chairman Bosch stated the Commission received some
correspondence from neighbors in the area indicating their
calculations that the amount of dust to be generated during
the course of normal grading activities would be a rather
substantial impact on them. And the concern about the shut
off at 15 mile per hour wind velocity across the site that
is required by AQMD or grading ordinance.
Mr. Burnett responded they were sensitive to the problems
created by grading and are willing to abide by the
guidelines to control the dust and will try to mitigate the
inconvenience.
E.I.R. QUESTIONS & ANSWERS:
Q.1. The E.I.R. was prepared for a more dense project
than the project currently before the Planning
Commission. Is the E.I.R. legally in conformance
with CEQA?
In addition to the response before the Commission, advice
from Legal Counsel was sought.
Mr. Herrick said the change in project does not, as a matter
of law, invalidate the E.I.R. because a single family
alternative is included as a study alternative. And the
single f amily alternative is a less intensive land use than
the primary alternative. The Commission still has the
obligation under the law to examine the report, to make
findings with respect to the adequacy of the study of the
anticipated impacts and proposed mitigation measures based
on the single family alternative.
Chairman Bosch stated the Commission received correspondence
from Gregory Hile, representing the homeowner's association.
Mr. Herrick briefly read through the letter at the meeting.
Mr. Hile will be asked to respond a little later.
Q.2. What about the specific differences between them
such as the creek and culvert?
No comment after reading the applicant's response.
MISCELLANEOUS QUESTIONS:
Q.1. Residents have questioned the proposed future of the
City owned parcel west of Cambridge which is
partially affected by the transition structure. Why
isn't this parcel included in the proposal? What is
the plan for it?
Punning Commission Minutes
October 9, 1989 - Page 27
No comment.
Q.2. Verify water and sewage capacity and how increased
capacity will be provided if needed.
Mr. Johnson has not seen a detailed study of the sewer
availability. He believes it is their intention to drain to
Cambridge, but there are some conditions that would require
off-site upgrading at trunk facilities to provide for that
capacity if necessary.
Q.3. Applicable staff report comments.
Chairman Bosch was concerned that the draft E.I.R. did not
include response to comments relative to some items in the
staff report. A general summary was requested of how they
are adequately responded to in the E.I.R..
Sid Linmark, PBR, Irvine, said the particular responses
before the Commission are resultant from the coordination
between three different documents. One was the staff
report, which was prepared by City staff. It did not have
access to the Response to Comments that were submitted
separately by them. This particular response attempts to
coordinate between those items. The first body of
information pertains to comments that were raised by the
County E.M.A. Planning staff as it related to traffic.
Particularly the level of service at Tustin/Chapman
intersection, the growth rate assumed by the traffic study
and the impact of the project on the Chapman and 55 on and
off ramps. All three of the issues were responded to in the
final E.I.R. and this particular material summarizes those
three responses. Item 45 of the staff report is a new
requirement of the Southern California Association of
Governments that a jobs/housing balance be achieved within
the region and this particular response provides data on
what the current job/housing issue would be in the City and
what impact this project would have on that ratio. The City
does not have a current goal for a specific job/housing
balance at this point in time. Items 51, 53, 54 and 55 have
been responded to by Keith Engineering. Referring to
exhibit B, as written on the staff report on Page 21, Item
53 related to the comment hydrology and what were the limits
of the 100 year flood. That particular exhibit is included
in the Draft E.I.R. Item 54, Page 21 of the staff report
related to the box culvert sizing and the cfs flows.
Item 55, Page 22 relates to the issue of whether an open
channel or a closed box channel could be achieved on site.
He believed Keith Engineering responded to that. Item 56,
Page 22 refers to the differing cfs's and has been resolved
in prior discussion. Item 58, Page 23 relates to the
estimates of earth work on site. The last item 60, Page 24
Planning Commission Minutes
October 9, 1989 - Page 28
relates to the estimation of trips related to fill being
brought on site. Item 61 related to the hauling operations
and mitigation is provided in the E.I.R. that would result
in the developer meeting with both City and Cal Trans to
find the most feasible route for import of fill into the
site. Staff report, Page 25, Items 63, 64 and 65 relate
either to the biological impacts and the wetland loss
previously discussed. Item 78, Page 31 of the staff report,
relates both to the curb-to-curb width of LaVeta and the
internal circulation access, discussed previously. Item 80,
Page 31, related to a comment about minimum lot size that is
now revised with the current plan.
Commissioner Greek commented there were no answers to the
responses. The responses are not answered adequately. He
felt the questions asked were very specific. There should
be a more definitive number provided.
Dick Vogel, Van Dyke Engineering, 1403 Batavia, stated on
the basis of 250,000 yards anticipated on the project, the
trucks yield about 14 cubic yards of compacted import per
load. Typical anticipated production rate on a project of
this nature would be approximately 200 loads per day. If
allowable, it could be expedited by double spreading on the
loaders at the pit location and making the operation go more
quickly. That is based on an average of 250,000 cubic yards
to end up with 17,900 truck loads. Dividing the 200 loads
per day, it would be a 90 day working operation based on a
five day, 8 hour day working week, or a 4 1/2 month import
operation.
Mr. Burnett added there have been some refinements to the
plans. Some of the original work that went into this was 1
1/2 years ago. As the plan has continued to unfold and
evolve, some of the information has changed. The planning
criteria with respect to grading has always been to keep it
to a minimum. Information has changed wherein the instance
of the Draft E.I.R. they used some worst case scenarios; as
the plan has been refined, it has become a better case
scenario. The cubic yardage has now diminished from 300,000
to 250,000 yards.
Commissioner Scott said one of the conditions in the staff
report required a bike trail from Cambridge to Tustin. He
believed one of the questions raised at the last study
session was to sacrifice some of the parking to extend the
greenbelt over to Tustin so that condition could be met. He
did not see it on any of the plans where that condition is
met .
Chairman Bosch responded that was true. Questions 17 & 18
made reference to that. Although the greenbelt may have
Planning Commission Minutes
October 6, 1989 - Page 29
been increased from the right-of-way with part of the
landscaping, that primarily the excess went into balancing
the lot sizes to increase the minimum lot size. It was also
anticipated that the greenbelt would extend past the
commercial portion so the bike lane could be taken off and
there is still not a greenbelt past the commercial portion.
John Killen, 271 S. Grand Street, in response to the bike
trails, they have made two or three adjustments. They have
met with Bernie Dennis and other staff members to discuss
the right-of-way, width and the ability to pull the bike
lanes off of LaVeta onto the open space adjacent to the
Rosewood connection, as well as the greenbelt on the
southerly side of the property. The overall goal was
twofold: one to try to create more open space adjacent to
the edges where the residences occur on the northerly and
southerly residential sites, as well as to extend the bike
lane/pedestrian access east/west through the property in the
form of a meandering path in the open space itself. The
bike trail is referred to on Pages 11 and 12 of the PC
"Circulation Plan".
Mr. Dennis thought the problem was that they did take the
bike trail off the street and put it in the meandering
configuration. He believed, per discussion, as long as they
replace the bike trail, the street section could be reduced.
That is what has apparently been done on the plan to
terminate the bike trail back into the minimal street
section and not extend it onto Tustin. There are two
options: either widen that section of the street to
accommodate the bike trail adjacent to the commercial
development, or continue the bike trail behind the curb on
up to Tustin Street.
Mr. Killen responded that was their intent. The graphic is
intended to show the extension of the bike trail to Tustin.
If that requires a widening of the park way adjacent to the
restaurant site, they will be able to accommodate that
through conditions. They have an excess of parking on the
restaurant site which would allow them to eliminate two or
three cars in that center parking island and create the
width required to extend the bike trail/sidewalk to Tustin.
Those speaking in opposition
Bob Bennyhoff, 10642 Morada Drive, was concerned about the
plan because of the 4,000 square foot lots. They have
increased them from 3,700 to 4,000. He made reference to
the lots in East Orange and it has led the City Council
Steering Committee and the Irvine Company to agree there
will be no 4,000 square foot lots in the East Orange
development. Orange should not set a precedent for this
development standard.
Planning Commission Minutes
October 9, 1989 - Page 30
Gregory Hill, P.O. Box 380, Running Springs, attorney
representing The Santiago Creek Homeowners Association,
addressed the issues noted in his letter dated October 9,
1989. He summarized some of their concerns. The City has
recently adopted a General Plan and now a developer wants to
change it. Regarding the Draft E.I.R. a number of different
issues could be addressed: Project description,
alternatives to the project (i.e., golf course), 7,000
square foot lots, and mitigation measures.
Ralph Masek, President of Santiago Creek Homeowners
Association, voiced the concern of confusion for surrounding
property owners. Many issues have not been resolved. The
City needs to address questions regarding the General Plan,
the 4,000 square foot lots -- why make changes to benefit
only a few people, should the City permit covering the
Santiago Creek and putting it in box culverts.
Wayne Spring, 1243 Fairway Drive, spoke about the sound
' levels and how it would affect the residences along his
street. LaVeta should not go through. He was also opposed
to the 4,000 square foot lots. The lifestyle of the
residents will be destroyed if this project were approved.
Dorothy Huduchek, 3196 North Hearthside, said this property
is listed on the Santa Ana River/Santiago Greenbelt Plan.
The County adopted the plan in 1971; the City adopted it May
18, 1976. The implementation was adopted by the City in
February, 1977 and is still in effect with the County by
Resolution 77144. Why not re-zone the property to open
space?
Bob Siebert, 1308 Fairway Drive, addressed the traffic
issue. It is difficult to get out on Tustin now. A traffic
light will not be a good thing for the neighborhood because
of the extra traffic.
Forrest Sweener, 927 East Fairway Drive, said there was not
enough open space in the City of Orange. This ground 20
years ago was not fit to have homes built on it. He thinks
their property values will go down because of this
development.
RPhuttal
Mr. Burnett said that contrary to what has been suggested,
the site is not the R-1-7,000 or R-1-6,000 zone that has
been suggested. Different housing alternatives are
contiguous to the golf course site. Their request requires
an increase in density of approximately one dwelling unit
per acre in excess of the current General Plan; to permit
lot sizes of less than 7,000; and to re-zone approximately 7
Planning Commission Minutes
October 9, 1989 - Page 31
acres of Tustin frontage for commercial use. If approved,
the plan would deliver: improvement of more than 3,000 feet
of Santiago Creek to a standard set for the 100 year flood;
it extends LaVeta Avenue 3,000 feet west from Tustin to
Cambridge and provides traffic control at both
intersections; it removes the 21 homes presently condemned
and abandoned and corrects the existing soils compaction
problem. All costs will be borne by the project. The
project further provides 1 1/2 acres of landscaped greenbelt
area, a commercial retail center expected to generate
approximately one million dollars per year in sales tax and
create employment. The project will also increase the
property tax base of the City by more than 70 million
dollars and provide a reasonably priced in-fill housing
option that otherwise would not exist in the City.
Development of this site under the current R-1-7 zoning
could not support the cost of infrastructure the plan
provides. Development under the R-1-7 zone would result in
a reduction or loss of the landscaped greenbelt area. The
cost of land acquisition and improvements for the LaVeta
extension would be passed on to the taxpayers. Clean up of
the 21 home site would not be possible and increased housing
prices in the project would result.
The public hearing was closed.
Commissioner Greek stated normal procedure was to begin with
the E.I.R. process, but he disagrees with the answers he
received. He would only be asking for more clarification
and perhaps skirting the issue that the developer is asking
for - a review of the plan. He had the same concerns as the
audience: lot size, traffic, the need for LaVeta (is it
really needed?).
The Commission sought staff's advice on how to proceed and
in what order?
Mr. Herrick said normal procedure begins with review of the
E.I.R.; before any project is approved, the environmental
study must be approved. He doesn't know if there was any
constraint in going the other direction.
Commissioner Greek was still undecided about the need for
the LaVeta extension. If it is needed, why isn't it built
to a standard secondary highway cross section as opposed to
this modified section?
Mr. Dennis stated the street started out as a conventional
64 foot secondary highway within a 2 or 4 foot lesser
right-of-way section. The cross section was 64 feet. The
Commission asked that every effort be made to provide
additional landscaping and the requirement was placed to
Planning Commission Minutes
October 9, 1989 - Page 32
provide a bike trail within the project area. Pursuant
discussions led staff to believe capacity was needed. Staff
opted for the narrower section to end up with a five lane
facility. They traded the street section off for
landscaping.
Chairman Bosch added he helped pursue that issue because his
concern was that you have an adequate street section for
vehicular safety and capacity. Bike trails is an expressed
concern and if it's to share major streets, why not get it
off and increase the landscaping. Is there a way to
dramatically increase the available greenbelt through the
site? One way to get the bike trail outside the curb, but
he doesn't know why that should affect what the standard
lane widths would be on a street without a bike trail.
Mr. Dennis said the changes to the cross section is a
reduction in the section. The original plan showed on
street bike lanes, four travel lanes, left turn lane, and a
raised island. The bike lanes/bike trail went up onto the
sidewalk area, the raised islands became painted islands,
which allows a reduction in the number 1 lane width because
they are not running next to a barrier. The curb lanes
have always been at 14 feet. The shrinkage in right-of-way
was from 75 to 70. This is not a standard secondary street.
Commissioner Master felt the lot sizes were not acceptable,
nor the routing of the street.
Chairman Bosch stated this was a difficult project. The
applicant does have private property rights and the existing
zoning he could work to. The question becomes, is there a
better plan than this? He concurs with Commissioner Greek's
concern that there is no solid evidence that the LaVeta
extension is necessary or that there might be some other
mitigations that could be performed other than the LaVeta
Street to take care of some of the traffic problems in the
community. He has heard a lot of talk about the 4,000
square foot lot being too small and the precedent it might
set. He is also concerned, but his response to that is that
the Commission has not seen adequate design for housing
units of 4,000 square foot lots. That's part of the
problem. It relates to Floor Area Ratios, development
standards set for the lots, relates to expectations on how
big a house we have to provide for all aspects of the
community and the sale price of that. He was not convinced
that 4,000 square foot lots can't be handled. He is willing
to look at smaller lots for a site where a precedent will
not be set. The trade off is retention of open space in a
significant way. He was hopeful to see a redesign of the
project that not only would increase the smallest lot size,
and add to more open space and greenbelt area. There is
Planning Commission Minutes
October 9, 1989 - Page 33
still excessive parking relative to code minimum
requirements in the commercial areas, which is beneficial
from the point of view of flexibility of use of those
buildings, but it doesn't accrue any gain to the greenbelt.
The project is overburdened with too much public
infrastructure requests. The greenbelt plan alluded to does
include a cross section of Santiago Creek that shows placing
it in box culverts with a park over the top. That is the
significant difference. He prefers the culvert with the
greenbelt on top than the 3 sided concrete open top box with
chain link fences down the sides. We're overburdening it
with the street on top of that. It appears the applicant
can't get to the economic trade off, which he has to have.
He prefers to have the greenbelt in lieu of the lot size and
in lieu of the street.
Commissioner Greek highlighted the responses he felt did not
get adequate answers: Site plan floor area ratios,
greenbelt areas, narrow parcel width for driveways, parking
questions, lot size conflicts with the East Orange General
Plan, strip zoning on Tustin (commercial and depth), depth
of the garage and front yard setbacks, density of
development (190 units), greenbelt area extension, problem
of parking at the restaurant adjacent to the residential
units, LaVeta extension, quantity of dirt cover for the
culvert, and the difference between 250,000 yards vs.
360,000 yards should be resolved.
Mr. Herrick suggested that any motion to the E.I.R. should
address findings with respect to the adequacy of the study
of impacts and mitigation measures. Comments concerning the
site plan may or may not be directed to particular findings
of adequacy with respect to mitigation measures.
Mr. McGee stated the normal sequence of events is as listed
in the original staff report. The Environmental Impact
Report is the first action to be taken. As a reminder, it
is an advisory document to all of the other actions taken.
The Overriding Consideration is to come to a conclusion
whether this Environmental Impact Report is prepared
consistent with CEQA requirements and does provide you with
adequate information to come to a decision. Irregardless of
what the position may be on the project itself, that is the
first decision the Commission is required to make.
Chairman Bosch stated his concern about the Environmental
Impact Report is in the Overriding Considerations about the
adequacy of response to the need or and mitigation of the
LaVeta extension. With regard to the Flood Control issues,
given all the testimony heard from different sources, it
appears that to the extent the Commission could rely upon
proper design and approval processes that it is reasonable
Planning Commission Minutes
October 9, 1989 - Page 34
to assume that the information will result in a proper
drainage structure. The key concern is the impact of the
street.
Discussed ensued between Commission and Legal Counsel
regarding the Environmental Impact Report.
Moved by Commissioner Bosch, seconded by Commissioner Greek,
that the Planning Commission recommend the City Council find
that E.I.R. 1143 has been prepared pursuant to the
requirements of CEQA but that the Statement of Overriding
Considerations with appropriate findings is not satisfactory
and it does not adequately address the full scope of the
impact nor necessary mitigation measures to off set specific
impacts identified in the E.I.R. as iterated by the
Commission's discussion.
AYES: Commissioners Bosch, Greek, Master, Scott
NOES: None
ABSENT: Commissioner Hart MOTION CARRIED
Mr. Herrick was approached by the applicant who requested a
continuance for an opportunity to address the concerns of
the Commission.
The Commission thought it was a mistake to grant a
continuance. They have voiced their concerns at previous
meetings and those concerns were not addressed.
Moved by Commissioner Greek, seconded by Commissioner Scott,
that the Planning Commission recommend the City Council deny
General Plan Amendment 1-89 "B", Zone Change 1068, Tentative
Tract Map 13901, Conditional Use Permit 1589 and
Administrative Adjustme nt 8923.
AYES: Commissioners Greek, Master, Scott
NOES: Commissioner Bosch
ABSENT: Commissioner Hart
MOTION CARRIED
Chairman Bosch voted no not because he disagreed that LaVeta
is wrong or some of the other issues, but he would have
liked to see another chance to get a suitable project
through. He did not find the one before them appropriate,
but on the other hand, he wanted to work for another chance.
Mr. Godlewski stated this item will proceed to City Council
for final action.
P~_anning Commission Minutes
October 9, 1989 - Page 35
IN RE: ADJOURNMENT
Moved by Commissioner Scott, seconded by Commissioner
Master, that the Planning Commission adjourn.
AYES: Commissioners Bosh, Greek, Master, Scott
NOES: None
ABSENT: Commissioner Hart MOTION CARRIED
The meeting adjourned at 12:20 a.m.
/sld