RES-8276 Approving Tentative Tract No. 14847RESOLUTION NO. 8276
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ORANGE UPHOLDING THE RECOMMENDATION OF THE
PLANNING COMMISSION OF THE CITY OF ORANGE AND
APPROVING THE SUBDIVISION OF PROPERTY SITUATED
WEST OF PROSPECT STREET BETWEEN THE COLLINS
AVENUE BRIDGE AND WALNUT AVENUE.
TENTATIVE TRACT 14847
APPLICANT: BEAZER HOMES CALIFORNIA, INC.
RECITALS:
After report thereon by the Planning commission and after
due public hearings as required by law, and after receiving a
recommendation from the Planning Commission, recommending, by
Resolution No. PC-51-93, that the subdivision
of property situated west of Prospect street between the
Collins Avenue Bridge and Walnut Avenue be approved, the City
Council considered Tentative Tract 14847 and determined that the
recommendation of the Planning commission should be upheld and
Tentative Tract 14847 be approved. Subject property is
more particularly described on Exhibit "
A" attached.During the public hearing, the city Council found
the facts
as follows:1. The site is irregularly shaped and approximately 23
acres in size located west of Prospect street between
the Collins Avenue bridge and Walnut Avenue (the northerly
two-thirds of the Rock
Creek Residential Development).2. The applicant is requesting approval of
a Tentative Tract Map and Conditional Use Permit to allow
the development of the subject site with a 423 dwelling
unit Planned unit Development. The proposal includes the
creation of 154 lots, of which 131 lots do not have direct
access to a public street. The proposal will replace
the northerly two thirds of the previously approved Rock
Creek
Ranch townhouse development.Orange Municipal Code (OMC) Section 16.
08.010 permits Planning commission review of a Tentative
Tract Map subject to the requirements of the Subdivision Map Act and
Title 1,6 of the OMC. Also, OMC Section 17.66.
040 requires approval of a Conditional Use Permit to create
a Planned Unit Development, and OMC Section 17.94.050.
A requires approval of a Conditional Use Permit prior to
creating lots
without street frontage.3. The subject site is designated by the City'
s General Plan Land Use Policy Map as Low/Medium Density
Residential, 6 to 15 dwelling units per acre, and the site
is zoned R-
3 Residential Multiple-Family) District.4. The subject site was
Company, and a history of the previously approved
applications that affected the site are as follows:
A. The Conrock Company owned 110 acres of land located
south of Collins Avenue, north of Spring Street, and on
both sides of the Santiago Creek. The majority of the
Conrock property east of the santiago Creek channel had
been used for building material extraction and
contained four open pits, with one pit approximately
125 feet deep.
B. In 1984 the City Council approved a General Plan
Amendment in 1984 and Zone Change 1008 that designated
the portions of the site adjacent to the santiago Creek
bed between spring Street and Collins Avenue for
multifamily development, and the easterly portion of
the site between Walnut Avenue and Bond Avenue for
single family development. The original approval also
required a new alignment for Prospect Street so as to
directly connect Chapman Avenue and Collins Avenue, and
improvements to the Santiago Creek Channel.
The Council's 1984 approvals allowed the development of
the 110 acre site with a total of 650 - dwelling units,which
were to be a combination of singe family,townhouse,
and mobile homes.C.
In 1984 the City Council also certified Environmental Impact
Report 861 as addressing the environmental impacts
of the proposed 650 dwelling unit development.D.
In 1987, the city Council approved Tentative Tract Map 13098
and Conditional Use Permit 1633 to allow 10 acres of
Conrock's 110 acres) located west of the Santiago Creek
channel to be developed with 84 town houses (the existing
vista santiago Townhouse Development).E.
In 1989, the city Council approved a rough grading plan for
the remaining 100 acres that included filling in the
large pits and regrading the site to allow for development.
F.
In 1989, the City Council also approved Tentative Tract Maps
13841 and 13842, Zone Change 1104-88, Conditional
Use Permit 1738-88, Variance 1855-
88, and Administrative Adjustment 88-
13, and certified Supplemental Environmental Impact
Report (SEIR) 861.Approval of these requests permitted
the development of approximately 71 acres north of Walnut
Avenue and west of the new alignment of
prospect Street with multifamily residences, and east
of Prospect Street with single family
residences. The proposed developments contained 485 condominium
units and 73 single family units, for a total of
558 dwelling units.Approval of these applications were
subject to 76 conditions (Which include
19 mitigation measures Reso
required by SEIR 861).
was wait Homes and the
Creek Ranch.
The applicant for this proposal
development was called Rock
5. As of September 1, 1993, the Rock Creek Development has
completed the rough grading of the site, the construction of
the santiago Creek improvements, the new alignment of
prospect Street, and the construction of 60 multifamily
units. The single family project located east of Prospect
Street has not been started.
6. The subject site has been rough graded and slopes downward
from Prospect street towards the santiago Creek channel.
The majority of the site's easterly perimeter is screened
from Prospect Street by a 6 foot high masonry wall and
landscaping.
7. Primary access to the site is via Prospect Street, which is
designated by the City's Master Plan of streets and Highways
as a "Secondary" arterial highway with an ultimate right-
of-way width of 80 feet. Prospect Street is fully
improved with two travel lanes in each direction, and
landscaped parkways and median
island.8. The surrounding land uses include the vacant property
owned by the applicant zoned R-1-6 and
single family residences zoned R-I-7 (Residential,
Single Family, minimum lot size 7,000 square feet) to the
east, an abandoned gravel quarry under County jurisdiction
to the northeast; condominiums and apartments across Santiago Creek zoned
R-3 to the west; -and the condominiums
within the Rock Creek Ranch
development zoned R-3 to the south.9. The applicant is proposing
to develop the 23 acre site with two
distinct products: 201 condominium units, and
100 attached single family residences. The condominium development is proposed
to be located on the site's southerly 13.
60 acres, and the attached single family residences on
the site's northerly 9.40 acres.The
proposed projects will replace the northerly two-thirds
of the approved Rock Creek Ranch condominium development.Of
the previously approved 485 dwelling, only the southerly 122 units
will be built. with construction of this project,
the total unit count will decrease to 423.10. Tentative
Tract Map 14847 proposes to subdivide the site
into 154
lots to be used
as follows:LOT DESIGNATION
Lots #1
through #36 Lots #137
through #136 Lot #137
Lots #138
through #
142 Lots "A"
through "L"LAND USE
Condominiums Attached Single
Family A communal recreational
area Public Landscaping area
The condominium lots range in size from 7,405 square feet.
to 19,166 square feet and will contain from two to six units
each. The attached single family lots range in size from
2,300 square feet to 3,500 square feet and each will contain
one dwelling unit.
11. The condominium units will range in size from 979 square
feet to 1,532 square feet, while the attached single family
residences will range in size from 1,433 square feet to
1,885 square feet.
The condominiums are grouped three to six units per build-
ing, each building two stories in height. The condominium
proposal includes 6 floor plans, of which three are two
story townhouses, and three are single level units placed
over the garages (referred to as carriage units).story
townhouses, and three are single level units placed over the
garages (referred to as carriage units).
12. The building setbacks from Prospect street will be a minimum
25 feet for the condominium buildings and will range from 15
feet to 55 feet for the attached single family units. The
building setback from the santiago Creek channel right-
of-way will be a minimum 10 feet for the condominium
buildings and will range from 6 feet to 8 feet for the attached
single family
residences.The condominium buildings will have a minimum
building separation of 15 feet when the buildings are side by
side and 25 feet when the buildings are back to back or when
two private yard areas are
adjacent.The majority of the single family units are attached by
one wall to one other unit, and have a minimum 10 feet
building separation from other
units.13. The proposal provides 681 parking spaces on-
site. The parking provided includes 602 garage spaces and
79 open parking spaces. The condominium development will
have 49 parking spaces either located in building
courtyards or perpendicular to the private drives, while
the attached single family will have 30 parallel on-
street spaces. All 301 units are provided with a
two car garage.14. External access to the proposed developments will
be via two unmanned gated entryways, one located onto
Walnut Avenue and the other onto Prospect street. The
Walnut Avenue entryway was built as part of the original Rock
Creek Ranch develop-ment and existing private streets in
the development provide access through the development. The
Prospect street gated entry way will be built opposite to Bond
street at its intersection
with Prospect street.The proposal is not designed to
include gated entryways between the existing townhouse
development and the proposals, or between the condominium
development and the attached
single family residences.Reso
The Prospect street gated entryway is anticipated to be the
project's primary entrance and will be designed to have a
car turnaround, three parking spaces, stacking for four
cars, and a directory outside the gate. The Walnut Avenue
gated entry drive is the secondary entrance and was designed
to have a car turnaround outside the gate, stacking for two
cars, and a directory outside the gate.
15. The internal access to the residences will be via private
streets and drives. The private streets will either be 28
feet in width without on-street parking, or 32 feet in
width with parallel parking on one side of the street.
The private drives will have a minimum width of 25
feet.16. The proposal includes a communal recreational facility on
an 18,730 square feet parcel located towards the center of
the site. The communal recreational facility will contain
a swimming pool, a Jacuzzi, a pool cabana, and a
barbecue
area.17. The proposed condominium and attached single family
develop-ments will be incorporated within the existing
Homeowners Association for the townhouse development. The
Homeowner Association will be responsible for the maintenance of
the private streets and drives, the commonly owned
landscaping areas, the communal recreational facility, and
patio fencing. The proposal includes CC&Rs that will
indicate permitted construction material, exterior colors,
etc.18. The proposal includes double trash enclosures for both
the condominium and attached single family residences.
The enclosures will be located within the condominium building'
s courtyards or on the private street for the attached
single family
residences.19. Due to the 28 foot grade differential from the
Collins Avenue bridge to the project's southerly property line,
the proposal includes the construction of several
retaining walls and the grading of several large slopes. The
largest retaining wall is proposed along the site's
easterly boundary and near the existing perimeter wall. This
wall will range in height from 6 feet to 10 feet and will have
a separation from the existing wall of 1 foot to 40
feet.There are also numerous smaller retaining walls
located through-out the project (as were included in
the previous
approved project).20. Private patios and small rear yards are provided
for the larger condominium units and the attached
single family residences. Also, to improve the utilization of
the private yard space for the attached single family
residences, the tentative tract map includes a 5 foot wide easement
for open space and recreational purposes to be assigned to
from one parcel to the neighboring parcel. The easement allows
for a fenced in 10 foot wide side yard area on one side
of the residence and zero yard space on the other, as
oppose to 5 Reso
having a 5 foot setback on both sides of the residence.
21. The project does not include any public improvements since
the applicant has completed the improvements for the
originally approved Rock Creek Ranch development. The
public improvements completed included a new alignment for
Prospect street, channeling of the Santiago Creek bed,
extension of Walnut Avenue from Prospect Street to santiago
Creek, the grading and landscaping of a 1 acre park site at
the end of Walnut Avenue, and a bike trail along the Creek.
22. The proposal's overall site density of approximately 13
dwelling units per acre is consistent with the Low Medium
Density Residential General Plan designation of 6 to 15
dwelling units per acre established in 1984 when the City
council approved the General Plan Amendment in 1984 and Zone
Change 1008.
14.9 dwelling units/acre
201 dwelling units/13.60 acres
10.4 dwelling units/acre
100 dwellinq units/9.58 acres
13.0 dwelling units/acre
301 dwelling units/23.18 acres
23. The applicant's proposal for a condominium and a planned
unit development is regulated by the orange Municipal Code
Chapter 17.66, Planned unit Developments and Condominiums.
The intent of Chapter 17.66 is to encourage more imaginative
and efficient residential projects than can be developed by
strict adherence to the Zoning Ordinance base zone require-
ments, by allowing flexibility in establishing development
standards. Also, this Chapter's intent is to create a wider
variety of housing types and greater areas of open space by
reducing the amount of land needed for public streets,
easements, etc.
Condominium
Attached Single Family
Combined
To achieve the intent stated above, Chapter 17.66 estab-
lishes only two development standards; the maximum site
coverage and off-street parking requirement.
Although Chapter 17.66 also addresses maximum site density,
previous City Council approvals specific to this site and
as discussed above, supersede this Chapter. The
applicable standards are based on the zoning classification of
the subject property, which in this case is R-3. Below
is a comparison of the code requirements and
the
proposal:REOUIREMENTS site coverage (area devoted
Max. 65%area devoted
to buildings,open parking,
and driveways,but not including
private
streets)
PROPOSED 60%Off-Street
Parking 677 spaces 2.
25 per
unit one covered
space per
unit)681 spaces 2.
26 per
unit 2
garage space/unit)Reso
No.
The proposed site coverage is less than the maximum permitted,
and the parking provided exceeds Code requirements.
The site plan shows 79 guest parking spaces, 47 provided for the
condominium development and 32 provided for the attached single
family development. Staff review of the site plan found that the
guest parking was equally distributed throughout the development.
24. Development standards not specified within Chapter 17.66, such as
building setbacks, building separation, and recreation and
leisure area, are proposed by the developer and determined by the
Planning commission and city Council at the time a site plan is
approved. The applicant's proposed site plan indicates the
following:
Condominium
product
Building Setback 8'
from private
street, drive or
driveway)
Building
Separation
15'
Driveway depth less than 9' or
greater than 18'
Private Patio &
Yard Space
Two story - 250 sq.
ft.carriage
unit -none Common
Recreational
Area
13,
000
sq. ft.provided for
both developments.
Sinqle
Familv
front -3'
side -5'
or 0'rear - 5'
10'less than
3'
or greater than 18'
900 to 1,
200 sq.ft.The communal
recreational
area indicated above is about one-third less than
the area indicated on the tentative tract map (Lot 137) since
the parcel has several extensions that are too narrow or steep
for any use.The previously
approved townhouse development provided two recreational areas
that had a combined area of approximately 22,000
square feet of usable recreational area.The proposal
provides 43 square feet of recreational area per dwelling unit,
and compares to other developments as follows:Western National
Properties, Santiago Hills 88 sq. ft.junit Standard Pacific
condominiums, Santiago Hills 56 sq.ft.junit Inter American,
Santiago Hills 47 sq. ft.junit 25. Chapter
17.66 of the Orange Municipal Code requires building height within
PUD's to comply with the base zone require-7 Reso
No. 8276
ments unless the Planning commission makes specific
exception in approval of the Conditional Use Permit. The
building elevations indicate the condominium and attached
single family structures will have a maximum height of 35
feet, which is 5 feet' higher than that allowed for
developments in the R-3
District.26. The applicant has included a restriction to be placed in
the C,C & Rs that there shall be no building additions
that increase the usable square footage of any of the
dwelling units. The C,C &Rs will make allowance for minor
building improvements, such as bay windows and sky lights, subject
to approval of the Homeowners
Association.27. The Conditional Use Permit application includes a request
to allow the creation of 131 lots without direct access to
a public street. The intent of requiring a Conditional
Use Permit is to allow for flexibility in subdivision design
and to ensure that all parcels to be created will have access
to public streets, including by private streets and drives.
To ensure that the proposed parcels will have permanent
access to public streets, the tentative tract map includes
Lettered Lots "A" through "L" that contain private streets
and drives, and the recommended conditions require
that ingressjgress easements for all parcels be included with
the tentative tract
map.28. The Design Review Board reviewed the proposal
and preliminarily approved the building elevations,
building materials, and landscaping
plans.29. The Environmental Review Board (ERB) reviewed the
proposal and had the following
comments:A. The proposal does not require additional
environmental review since EIR 861 & SEIR 861 have already
addressed the environmental impacts of development of
multifamily residences on the site, at a similar
density.Furthermore, the mitigation measures applied to
the previous projects are included with the
recommended conditions for the present
applications.B. The numbered lots indicated on the tentative tract
map for common open space, landscaping area, and
the communal recreational area should be designated
as lettered lots so as to prevent the development of
these parcels for private purposes, such as
additional dwelling units or larger private
yards.C. The project's southerly division property line
was established by Lot Line Adjustment 92-9,
which adjusted several lots lines of Tract 13841 to
match the applicant's planned build out of the
townhouse portion of the Rock Creek
Ranch development.D. The proposed development conforms to the City'
S zoning Ordinance requirements regarding parking,
lot coverage,Reso No.
and unit sizes are consistent with R-3
requirements.E. To assure that no additional vehicular access
points onto Prospect street are established, a
condition recommends that all access right onto Prospect
street other than at the gated entry shall be assigned to
the City of
Orange.30. The Planning Commission, when making the determination
for the proposal, must decide that the applicant's site
plan,with the proposed building setback, recreational
and landscaping area provided, and reduced driveway length, is
a superior development over a conventional
development.NOW, THEREFORE, BE IT RESOLVED, by the city Council of
the city of Orange that Tentative Tract 14847 be approved for
the following
reasons:1. That the Tentative Tract Map conforms to the City's
General Plan and Zoning
Ordinance.2. That the Tentative Tract Map conforms to the procedures
and practices of the city's Subdivision
Ordinance.BE IT FURTHER RESOLVED that Tentative Tract 14847
be approved subject to the following
conditions:1. Development shall be in substantial compliance with plans
as approved by the Planning commission and on file with
the Department of Community
Development.2. The Design Review Board will review and approve
final building elevations, and landscaping plans prior to
issuance of building
permits.3. Copies of the Supplemental Environmental Impact Report
for this project will be available at the sales office and
the previous use and condition of the property shall be
fully disclosed to potential new
residents.4. If, in the future it is found the project will require
the hauling of any import/export of soil, the haul routes
will be established by a hearing of the Planning
commission.5.* That no construction take place between 7:00 P.M. and 7:
00 A.M. on weekdays and Saturdays, or at any time on Sunday
or Federal
Holidays.6.* Developer shall utilize energy efficient built-
in appliances to aid in conservation of energy resources.
Developer shall certify compliance with a written statement to
Department of Community Development prior to issuance of
building permits.7.* All residential construction must comply with
the State Energy Insulation Standards (Title 24) and City
of Orange Building Codes in effect at the time of
application for building permits. The building permits have to
be noted 9 Reso
that the plans conform to the state standards at time of
issuance.
8.* That the applicant provide Pacific Bell Telephone with four
to six months lead time to deal with transitionally the
existing telephone facilities with the addition of the
facilities needed for the project. The applicant shall
submit to the Department of Community Development the
applicant's notification letter to Pacific Bell.
9.* That glare from the private street lighting shall be
shielded, screened, and/or oriented so as to not be seen
from any point beyond the exterior boundaries of the
property and so that the source shall not be a nuisance to
any point beyond the exterior boundaries of the property or
cause illumination in the surrounding residential areas in
excess of 0.5 foot-
candles.10. Additions to individual condominium units are not
permitted.Alterations such as bay windows, skylights and
interior modifications are allowed upon approval of city
Building
Permits.Conditions 11 through 40 shall be complied with to
the satisfaction of the City's Public Works Department and other
City Departments as
noted.11. Subject to conditions of Addendum Sheet No.
1.12. Monuments shall be set based on a field
survey.13. Construct any remaining portions of Prospect Street
not constructed with Tentative Tract Map
13842.14. Proposed numbered lots #137 through #142 shall
be redesignated as lettered lots "M" through "
R".15. Any existing utilities, within Tentative Tract Map
14847 boundaries, constructed with Tract 13841 and that do
not meet standard locations within new proposed private
streets shall be removed and reconstructed as approved
on improvement plans for Tentative Tract Map
14847.16. Private streets shall be constructed to private
street standards as required by the Department of Public
Works.17. Vehicular access rights to Prospect Street shall
be dedicated to the City of
Orange.18. Sidewalks on private streets shall be constructed to
provide a minimum of 4 feet between outside edge of walk and
any obstructions (fire hydrants, street lights, mail
boxes,etc.) installed behind the
curb.19. Private streets shall have "No Parking at Any Time"
signs installed as required by the city Engineer. At those
areas where parking is specifically provided, the developer
shall Reso No.
8276
10
install "Parking permitted in designated spaces only" signs.
20. Subject to dedicating an ingress/egress easement over
private streets to City of Orange for public related
functions.
21. C,C& R's to be reviewed and approved by the City Attorney's
office and Department of Community Development prior to
approval of final map.
22. Construct storm drain to City standards.
23. Dedicate and construct sewer system to city standards.
24. subject to installing cable television facilities as
required by City's franchised cable TV companies. This
shall include easement rights to buildings being served.
25. All peripheral fencing/block walls shall be constructed
within tract boundaries.
26. Erosion control facilities shall be installed after rough
grading per approved erosion control plan.
27. A final tract map shall be recorded within 24 months after
tentative approval and prior to the sale or lease of any
lot.
28. That an on-site dedicated waterline be installed as
designed by City Water
Department.29. That a 15' easement over private streets be dedicated
to include water main, meter, detector checks and
fire
hydrants.30. That each building be water metered separately
unless otherwise approved by the Water
Department.31. That the developer satisfy all water main connection
charges as determined by the Water
Department.32. That developer shall pay all Water Department fees
and charges prior to City council approval of final tract
map.33. Proper sight distances shall be provided at Prospect
street
entryway.34. Install traffic signals at the Prospect Street/spring
street
intersection.35. That the necessary easements and/or rights of entry at
the proposed signalized private road entry at
Prospect street/Bond Avenue, be granted to the
City.36. Final design of gated entrance shall be reviewed
and approved by the city Traffic Engineer prior to approval
of Final Tract
Map.11 Reso No.
37. That the gated entry at Prospect street/Bond Avenue be
provided with a minimum 100' throat to accommodate a five
vehicle queue.
38.* The applicant shall follow all mitigation measures listed in
Supplemental Environmental Impact Report #861 regarding site
grading.
39.* Restripe Chapman/Prospect to provide room for south bound
right turning vehicles. The existing striping of the north
and south legs can be shifted three feet east to provide a
19 foot south bound curb lane which the County of Orange
Growth Management Plan considered to be a through lane and
an unofficial right turn lane.
40.* The developer shall pay County Sanitation District #2 fees,
and City of Orange connection fees. A receipt for both fees
shall be filed with the Department of Community Development
prior to issuance of building permits.
The following conditions shall be complied with to the
satisfaction of the City's Crime Prevention Bureau.
41. That all windows and doors opening onto the courtyards for
the stacked flat condominiums shall have upgraded hardware
to protect against break-
ins.42. An address directory shall be illuminated at each entry,
at a location not obstructed by landscaping or cars
and approved by the Crime Prevention Bureau and Design
Review
Board.43.* All structures shall comply with the requirements
of Municipal Code - Chapter 15.52 (Building Security
Standards), which relates to use of security hardware,
doors, windows, and lighting (Ord 7-79). "Approved
products list 4/92" is
available.44.* All landscaping shall be maintained so that it does
not interfere with the required addressing or areas that
are required to be
illuminated.45. Additions to individual condominium units are not
permitted.Alterations such as bay windows, sky lights, and
interior modifications are
permitted.46. Perimeter landscaping and wall shall be maintained by
a homeowners association or landscape maintenance
district.47. Developer shall construct recreation trail along
santiago Creek per City standards. Trail development shall
be designed to link other existing or proposed
recreation trails in the area and approved by the community
Services
Department.48. All parkways shall be developed with landscaping and
City Reso No. 8276
12
street trees.
49. All street plantings to include the installation of root
barriers on the sidewalk side of the tree, or where
conditions warrant, the installation of a deep root box as
directed by the Community services Department.
50. Irrigation systems designed with a loop pressure main line
shall have a single P.O.C. per city Water Department
requirement.
51. Landscaping and irrigation plans shall be approved by the
Community services Department.
The following substantial code requirements are included for
information only. This list is not all inclusive of every code
requirement affecting this project.
Payment of the following fees as set at time of issuance of
building permits:
A. Transportation System Improvement Program (TSIP)
B. Major Thoroughfare and Bridge Program
C. Police Facilities Fees
D. Fire Facilities Fees
E. School Development Fees
F. Park Land Dedication Fees
The following requirements shall be complied with to the
satisfaction of the City's Police Department and other
Departments as noted.
Required lighting in the private street, parking area, and
drives shall meet the minimum requirements of 1 foot-
candle minimum maintained). The lighting plan shall
consider neighboring uses, not direct light onto, or create glare
for areas beyond the project, and shall include
photometrics showing compliance with 1
foot-candle.The Tract design shall incorporate the concepts
of Crime Prevention through Environmental Design (
CPTED). CPTED involves the placement and orientation of homes,
the access and visibility of common or public open spaces
and the design of recreational trail areas. These
designs shall promote public safety and physical security
while allowing the residents or public the ability to self police
their own
neighboring areas.Submit a fencing plan to be approved by the
Crime Prevention Bureau, Planning Department, and Design Review
Board, prior to issuance of any building permits. Fencing shall
be a minimum height of 6 feet above finished grade and
shall be of a non-climbable design. Fencing
around the internal common recreation areas shall be
a see-through design.All residential
structures shall display approved illuminated address device(
s) visible to
approaching
Reso
emergency vehicles. Each multiple family dwelling shall
display an approved illuminated 4" address number at the
entry door. Exact location, number of devices, and height
of structure number(s) will be determined during plan check
by the Crime Prevention Bureau.
Garage doors equipped with automatic garage door operators
shall be equipped with a secondary latching device to secure
the door against forced entry. The secondary latching
device shall be designed to work in conjunction with the
door operator and be approved by the Crime Prevention
Bureau.
Stairways providing exterior public access to the second
floor and second floor balcony railings or siding shall be
designed to provide see-through visibility above the
walking
surface.The following requirements shall be complied with to
the satisfaction of the City'S Fire Department and other
Departments as
noted.An approved fire sprinkler system must be
installed throughout the building per O.M.C. 15.32.080
section 10.306(a). The system shall be designed per N.F.P.A.
13,N.F.P.A. 13D or 13R, U.B.C. Chapter 38 and U.B.C.
standard 38-1. The sprinkler system requires 24
hour supervision.Fire sprinklers are required in residential buildings
5,000 square feet
or more.The Fire Department connection shall not be affixed
to the building. The fire department connection must be
located at least 40 feet away from the building, within 40 feet
of a fire hydrant, and on the address side of
the building,unless otherwise determined by the fire
department. The hydrant shall be located on the same side of the
street as the fire
department connection.Provide on-site fire hydrant(s) and
mains capable of supplying the required fire flow. The hydrant
model and on-site locations shall be approved by the
Fire Department and have a three (3) foot minimum
clearance around the circumference of the fire hydrant.
The on-site hydrants shall not be controlled by the control valve (
P.I.V.) for the sprinkler system so that water flow
to the hydrants is not impaired should the sprinkler system
be shut down for any reason. (U.F.C. 10.206 and 10.
301) Plans must be submitted
to the Building Department.The number and location of hydrants
shall be determined by
Fire and Water Departments.Prior to issuance of a fire
service (detector check) the required water supplies for
hydrants and fire sprinkler systems shall be determined and the
water supplies shall be approved
by the Fire Department.
Every building shall be accessible to Fire Department
apparatus by an access roadway of not less than 20 feet of
unobstructed width having a minimum of 13 feet 6 inches of
vertical clearance. the access roadway shall be extended to
within 150 feet of all portions of the exterior walls of the
first story of any building. An additional 8 feet is
required for parking; i.e. a fire apparatus access road,
with vehicle parking on one side, shall be not less than 28
feet in width. A fire access road with parking on both
sides shall be not less than 36 feet in width. U.F.C. sec.
10.207
Fire access lanes shall be signed and marked according the
City of Orange Fire Departments Access Standards.
The Fire Department access roadway shall be an all weather
driving surface capable of supporting the imposed loads of
fire apparatus, 40,000 pounds and shall not exceed the angle
of departure for fire apparatus on any slope. U.F.C. 10.201
14.
The Fire Department access roadway shall be
adequate turning radius for Fire Department
40 foot outside and 20 foot inside radius.)
provided with
apparatus. (A
U.F.C. 10.207
The proposed development is within a climatic and
topographic high hazard and fire zone (Ordinance 5-
87),which requires all buildings constructed in the zone to
have class A fire retarding roof with fire stopped and
enclosed eaves. In addition, a spark arrestor is required
on chimneys, maximum one-half inch
screen required.ADOPTED this 14 th day of
December 1993.
GENE BEYER Mayor of the City
of
orange ATTEST:By: Ma~
pro tern0['(~';
FZ;:
u Af/ .' "city Cle~o t City
of Orange I hereby certify that
the foregoing regularly adopted by the City
Council of regular meeting thereof held on
the 14 by the
following
vote: ----Resolution was duly
and the city of Orange at
a th of December ,
1993,
AYES:
NOES:
ABSENT:COUNCIL MEMBERS: SPURGEa'!, BARRERA, MAYCR BImR, =Z,
MURPEY COUNCIL MEMBERS: ~
lli COUNCIL
MEMBERS: ~tB (
k~~city Cler of ctty of
Orange SSH:dg 15 Reso No.
8276
EXHIBIT "A"
TTM 14847
Being a subdivision of Lots 13 to 16, Tract No. 13842, as shown
on map filed in Book 674, Pages 28 to 42 inclusive of Maps, and
Parcels 5 to 8 of Lot Line Adjustment No. LL-92-9,
both records of
Orange
County.